West Arthur's 4 GWh Battery: What a 500 MW Wind Farm and Australia's Longest Storage Bet Means for Queensland
A Western Australian developer has put one of the largest wind-and-battery proposals in the country into the federal environmental assessment system — and, in the same step, doubled the size of its battery. On 13 November 2026, West Arthur Energy, a project company of Western Australian developer Lacour Energy, submitted the West Arthur Wind Farm and Battery Energy Storage System project for review under the federal Environment Protection and Biodiversity Conservation Act, known as the EPBC Act. It was reported on 14 November 2026. This blog is about that 13 November referral, reported on 14 November — not about a decision, a financing, or a construction start, because none of those has happened.
The proposal is for a wind farm of up to 92 turbines, listed on the federal National Renewable Energy Priority List as a 500 MW project, paired with a battery of up to 500 MW and 4,000 MWh — 4 GWh, or about eight hours of continuous discharge at rated power. Most grid-scale batteries built in Australia so far store two to four hours of energy. An eight-hour battery is a different kind of asset: it can carry wind generation through the night and keep supplying power when the wind drops for hours rather than minutes.
It is equally important to say what this referral is not. It is not an approval. Federal environmental approval has not yet been obtained. The project is not financed and it is not under construction. A referral under the EPBC Act asks the federal government to decide whether a project is likely to have a significant impact on matters of national environmental significance, and if so, how it should be assessed. The developer's own estimates put construction at two to three years and first power in 2030, with an estimated commencement in July 2027 — estimates reported in October 2026, not confirmed dates, dependent on approvals, financing, procurement and grid connection that are all still to be settled.
This blog explains what was actually referred on 13 November 2026, why the battery doubled, what eight hours of storage changes, and what Queensland and Brisbane buyers should take from a Western Australian project connecting to a different grid, the South West Interconnected System.

What happened, when, and who is involved
What happened: West Arthur Energy submitted the West Arthur Wind Farm and Battery Energy Storage System for review under the federal EPBC Act on 13 November 2026. The referral covers a wind farm of up to 92 turbines and a battery of up to 500 MW / 4,000 MWh, together with about 15 kilometres of double-circuit 330 kV overhead transmission line to connect the project to the grid.
When it happened: the federal referral was submitted on 13 November 2026 and reported on 14 November 2026. It follows a state process that began a month earlier: the project was submitted to the Western Australian Environmental Protection Authority (EPA) on 15 October 2026, and a seven-day state public comment period ran from 26 October to 1 November 2026. The federal referral is the next step in that sequence, not the first step, and not the last.
Who is involved: West Arthur Energy, the project company; Lacour Energy, the Western Australian developer behind it; the Western Australian EPA, which received the state submission in October; the federal government, which will now consider the EPBC referral; and Western Power, which is planning the Codering terminal substation. The local community around Darkan and Collie is directly affected: the developer is already paying pre-construction grants and setting aside a community benefit fund.
Where it is: the project is in the Shire of West Arthur, Western Australia, about 3 kilometres south of Darkan and about 40 kilometres east of Collie. The total development footprint is about 10,996.76 hectares, but actual construction disturbance is far smaller — about 564.75 hectares, mostly previously developed agricultural land.
What has not happened yet: no federal approval has been granted. No financing has been announced. No construction contract has been signed. No turbine model has been finally selected — the final turbine number, model and installed capacity remain subject to procurement and approval outcomes. No construction start is confirmed, although the developer has estimated commencement in July 2027 and first power in 2030. What has happened is a referral, and a referral is a request for assessment, not a permission to build.
The project at a glance
Item | Detail |
Federal referral date | 13 November 2026, under the EPBC Act; reported 14 November 2026 |
Proponent | West Arthur Energy, a project company of Lacour Energy (Western Australian developer) |
Location | Shire of West Arthur, Western Australia; about 3 km south of Darkan, about 40 km east of Collie |
Wind farm | Up to 92 turbines; individual capacity 6–8 MW; maximum hub height 164 m; blade lengths up to 92 m; maximum tip heights up to 253 m |
Wind capacity | Listed on the National Renewable Energy Priority List as a 500 MW project; final turbine number, model and installed capacity subject to procurement and approval outcomes |
Battery | Up to 500 MW / 4,000 MWh (4 GWh); about 8 hours of continuous discharge at rated power |
Battery change | Up to 500 MW / 2,000 MWh when lodged with the local council in October 2026; doubled to 4,000 MWh in the 13 November 2026 EPBC referral |
Grid connection | About 15 km of double-circuit 330 kV overhead transmission line to the Codering terminal substation planned by Western Power; connects to the South West Interconnected System (SWIS) via the Clean Energy Link-East transmission project, currently under development |
Total development footprint | About 10,996.76 hectares |
Construction disturbance | About 564.75 hectares, mostly previously developed agricultural land |
Native vegetation clearing | No more than 5.67 hectares of native vegetation plus about 0.61 hectares of scattered farmland trees |
Protected species | Environmental surveys identified potential habitat and foraging areas for the protected black cockatoo; impacts to be controlled through turbine layout adjustment, limited clearing, and an adaptive management plan for birds and bats |
State process | Submitted to the Western Australian EPA on 15 October 2026; seven-day public comment period 26 October–1 November 2026 |
Federal process | EPBC referral 13 November 2026; federal review focuses on whether the project is likely to have a significant impact on protected species, ecological communities and other matters of national environmental significance |
National Renewable Energy Priority List | Provides approval coordination support only — it is not an approval |
Timeline (developer's estimates, not confirmed) | Construction 2–3 years; operational period about 60 years; estimated commencement July 2027; first power 2030 (per October 2026 reporting) |
Community benefit | Developer already paying pre-construction grants and setting aside a community benefit fund in line with state guidelines of $1,050 per MW of installed wind capacity (per October 2026 reporting) |
Status | Early stage: state submission and federal referral lodged; federal approval not yet obtained; not financed; not under construction |
Why the battery doubled — from 2,000 MWh to 4,000 MWh
The single most important development in the 13 November referral is not the wind farm. It is the battery. When the project was lodged with the local council in October 2026, the battery was described as up to 500 MW / 2,000 MWh. In the EPBC referral submitted on 13 November 2026, the battery is up to 500 MW / 4,000 MWh. The power rating is unchanged at 500 MW. The energy stored has doubled. The duration has doubled with it, from about four hours to about eight hours.
That doubling deserves a plain explanation, because the difference between MW and MWh is routinely blurred in headlines. MW is power; MWh is energy. A 500 MW battery can deliver up to 500 MW at any instant. A 4,000 MWh battery can deliver 500 MW for about eight hours before it is empty — or at a lower rate for longer. Doubling the MWh while holding the MW steady does not make the battery faster or stronger at any one moment. It makes it last longer.
Four hours was already long; eight hours is a different category. Most grid-scale batteries built in Australia to date have been sized at around two hours, and the more recent wave at around four hours. A two-hour battery suits the evening peak: it charges at midday when solar is abundant and discharges for the two hours when demand is highest and solar has faded. An eight-hour battery is designed for a different problem: wind generation that varies over many hours, a night longer than the evening peak, and a grid needing firm power for a sustained stretch, not just a sharp peak.
Why a wind project needs duration more than a solar project does. Solar follows a predictable daily shape, so a battery paired with solar mainly shifts midday energy into the evening. Wind does not follow the clock: it can blow strongly all night, drop away for hours, and return without warning. A short-duration battery fills when the wind blows and empties quickly when it drops, leaving hours of low wind uncovered. A longer-duration battery smooths that variability, storing a windy night's output for the morning or a windy afternoon for the evening and night. For a 500 MW wind farm, that smoothing is what turns variable generation into something closer to firm supply.
What the doubling signals — and what it does not change. It is reported that the battery was doubled between the October council lodgement and the November federal referral. The referral does not state a single reason for the change, and this blog does not invent one. But the direction is consistent with the wider storage market: batteries are getting longer, because the market is rewarding duration. A developer that doubles its battery's duration before securing approval is signalling that it expects duration to be worth paying for by the time the project is built, around 2030 on the developer's estimates. That is a commercial judgement, not a fact, and it will be tested by financing, procurement and market conditions still years away. Doubling the battery does not guarantee approval or financing, and the referral states no project cost, financing plan or revenue arrangement. Those are unknowns.
The wind farm and its footprint
The wind farm, as referred, would use up to 92 turbines, each of 6–8 MW, with a maximum hub height of 164 metres, blade lengths of up to 92 metres, and maximum tip heights of up to 253 metres. Those are very large machines by Australian standards: fewer, bigger machines capturing more energy at a greater height, where the wind is stronger and steadier.
Why the final number is not yet fixed. The referral states the wind farm as up to 92 turbines and the National Renewable Energy Priority List lists it as a 500 MW project, but the final turbine number, model and installed capacity remain subject to equipment procurement and approval outcomes. That is normal at the referral stage. Turbine models change, prices move, and approval conditions can require layout changes — moving a turbine, removing a turbine, or changing its height to reduce an environmental or visual impact. The "up to" in the referral is doing real work: it sets a maximum envelope for assessment, not a final design. A reader who quotes "92 turbines" as a fact about what will be built is overstating what the referral says.
The footprint versus the disturbance. The two area figures are easily confused. The total development footprint is about 10,996.76 hectares; actual construction disturbance is about 564.75 hectares, mostly previously developed agricultural land — a difference of roughly twenty to one, since most of the footprint would remain farmland. The disturbance figure, not the footprint, is the better guide to direct physical impact. Within it, no more than 5.67 hectares of native vegetation would be cleared, plus about 0.61 hectares of scattered farmland trees. Those are the numbers the federal review will scrutinise most closely, because even small clearing can affect protected species. What matters is what is in those hectares, not only how many there are.
The environment: black cockatoos, layout changes, and an adaptive plan
The federal review of the West Arthur referral will focus on whether the project is likely to have a significant impact on protected species, ecological communities and other matters of national environmental significance. That is the test under the EPBC Act, and it is a different test from the state EPA process that began in October. The state process and the federal process can run in parallel, but they ask different questions and can reach different conclusions.
What the surveys found. Environmental surveys identified potential habitat and foraging areas for the protected black cockatoo, a group of threatened species in south-west Western Australia. The surveys identified potential habitat and foraging areas; they did not, as reported, state that the project would destroy a particular nesting site or cause a particular number of deaths. Potential habitat is an area that could be used by the species; confirmed impact is a finding that the project would harm it. The referral is the step in which that question is put to the federal government for assessment.
How the scheme proposes to control impacts. It is reported that the scheme will control ecological impacts through three measures: adjusting the turbine layout, limiting vegetation clearing, and an adaptive management plan for birds and bats. Adjusting the layout means moving or removing turbines to avoid sensitive areas. An adaptive plan is adjusted in response to monitoring — for example, slowing turbines when bird or bat activity is high — so its effectiveness depends on the quality of the monitoring, the thresholds that trigger action, and whether the operator acts when they are met. Those details are the kind of thing the federal assessment would examine, and they are not yet public in the detail that would allow an independent judgement.
What is not yet known. The referral does not state that the project will have no significant impact, and it does not state that it will — that is the question the federal review must answer. Whether it is a controlled action, what level of assessment is required, and what conditions might be imposed are all unknown, and this blog does not speculate on them.
The grid connection: 15 kilometres, 330 kV, and a transmission project still being built
A wind farm and battery that cannot connect to the grid cannot sell power, so the connection is as important as the generation. The project would connect via about 15 kilometres of double-circuit 330 kV overhead transmission line to the Codering terminal substation planned by Western Power. A double-circuit line carries two circuits on the same towers, providing redundancy if one circuit is out of service. Fifteen kilometres is relatively short by Australian standards, but it is still substantial infrastructure, with its own footprint, clearing and visual impact.
The Codering terminal substation is planned by Western Power, the network operator in south-west Western Australia. The connection is described as being via the Clean Energy Link-East transmission project, which is currently under development — a key dependency, since West Arthur would connect to the South West Interconnected System (SWIS) through a transmission project that is itself still being developed. A project that depends on transmission still under development carries a timing risk that a project connecting to an existing substation does not. The same logic applies in Queensland: a project needing a new line or substation upgrade faces the same questions — is the capacity there, who pays, when will it be ready, and what happens if it is late? A 500 MW wind farm with a 4 GWh battery is only as useful as the line that carries its power to customers.
The process so far — and what happens next
The sequence shows how a large project is assessed when both state and federal processes apply. 15 October 2026: the project was submitted to the Western Australian EPA, the state environmental assessment process. 26 October to 1 November 2026: a seven-day state public comment period ran on that submission. 13 November 2026: West Arthur Energy submitted the project for review under the EPBC Act. Under that Act, a proponent must refer a project if it is likely to have a significant impact on a matter of national environmental significance, including nationally threatened species and ecological communities and migratory species.
What the National Renewable Energy Priority List does and does not do. The project is on the federal list, which provides approval coordination support — a single point of coordination to help a priority project navigate state and federal processes. It is not an approval, does not guarantee one, and does not override the EPBC Act. A project on the list still has to pass the same environmental tests as one that is not on it.
What happens next — and what is unknown. The federal government will now consider the referral and decide whether the project is a controlled action, and if so, how it should be assessed. This blog does not state a date for a decision, does not predict the outcome, and does not speculate on conditions. The state EPA process will also continue, and a project needs to satisfy both. The developer's estimates — construction in two to three years, an operational period of about 60 years, estimated commencement in July 2027, first power in 2030 — are estimates as reported in October 2026, not confirmed dates, and they will move if approvals, financing, procurement or transmission take longer than expected.
Why it happened now: the storage market is rewarding duration
The referral arrived in a month in which the Australian storage market was setting records. On Friday 6 November 2026, the amount of energy stored in batteries in the National Electricity Market (NEM) — the grid serving Queensland, New South Wales, Victoria, South Australia and Tasmania — reached a record 20.17 GWh. That shows batteries are now a material part of the NEM, and the question is shifting from "how much power can batteries deliver?" to "how long can they keep delivering it?" A single 4 GWh battery, as proposed at West Arthur, would be about a fifth of that record total on its own. The growth is not only at grid scale: under the federal Cheaper Home Batteries Program, which began on 1 July 2025, more than 600,000 batteries were reported as installed by 9 November 2026, as households store midday solar for evening use.
Two dated policy facts are relevant for Queensland readers. First, the Small-scale Technology Certificate (STC) step-down takes effect on 1 January 2027: solar deeming falls from five years to four years, and the battery STC factor falls from 6.8 to 5.7. Second, as at 15 November 2026, Clean Energy Regulator applications for mid-scale systems — 100 kW to 1 MW — are not yet open, and are expected in mid-to-late November 2026. Verify the current status with the Clean Energy Regulator before relying on a mid-scale application date.
What eight hours actually means. A 500 MW / 4,000 MWh battery can deliver 500 MW for about eight hours, or 250 MW for about sixteen hours, ignoring losses. In practice it would be operated to match demand and generation — charging when wind output is high and prices are low, discharging when demand is high. The eight-hour figure is a capability, not a daily routine: a two-hour battery covers the evening peak, while an eight-hour battery can cover the peak and keep going through the night, when wind is often strongest and demand lowest. It does not solve multi-day wind lulls — no battery can cover a three-day lull on its own — but it reduces the need for other firming. Queensland buyers know batteries mainly as household units of 5–15 kWh and grid batteries of two to four hours; an eight-hour, 4 GWh battery is twice the duration of the four-hour grid batteries now common, and 4 GWh is 4,000,000 kWh.
What this means for investors and developers
Duration is now a design choice, not an afterthought. The doubling of the West Arthur battery between October and November shows duration is being actively reconsidered during development. A Queensland developer should ask the same question: is storage sized for the evening peak, or for a longer stretch, and what happens to returns if the market rewards duration more — or less — than expected? Eight hours is one project's answer, not a universal one.
The referral is the start of a long process. Track the milestones: the federal controlled-action decision, the level of assessment, the state EPA assessment, transmission, financing and procurement. Each milestone passed reduces risk; each delayed increases it. The developer is already paying pre-construction grants and setting aside a community benefit fund in line with state guidelines of $1,050 per MW of installed wind capacity, as reported in October 2026. For a 500 MW wind farm that guideline implies a fund of the order of $525,000 — verify that figure against the developer's own statements before quoting it as confirmed. Community benefit is now an expected part of a large project, and a Queensland developer should have a clear answer on benefit and engagement before lodging, not after.
What this means for commercial and industrial buyers in Queensland
A 500 MW wind farm in Western Australia does not change the price of power for a Queensland factory, warehouse or shopping centre tomorrow — West Arthur connects to the SWIS, not the NEM. But it signals three things. First, long-duration storage will change the evening price shape. Batteries discharging for eight hours can supply power longer into the night and soften the evening price spike, which matters for a business that runs into the evening, such as a cold store, food processor or manufacturer on a late shift. Second, duration reduces curtailment. When wind or solar output exceeds demand or network capacity, generators can be curtailed. A larger battery stores energy that would otherwise be wasted; likewise, a Queensland business battery that is too small will fill by midday and leave afternoon solar to be exported at a low feed-in tariff. Verify your export limit and tariff before sizing a battery. Third, the connection question is the same at every scale. A Queensland commercial project depends on its own connection — Energex in South East Queensland, or Ergon Energy in regional Queensland. Ask what inverter capacity is approved, what export limit applies, whether the connection is basic or negotiated, what upgrades are needed and who pays, and how long it will take, before signing a contract.
What this means for homeowners in Queensland
Your battery and the grid's batteries are part of the same system. The 600,000+ household batteries and the grid-scale batteries that reached 20.17 GWh stored in the NEM on 6 November 2026 are both storing midday solar and releasing it in the evening. Duration matters at your scale too. Size from the load shape, not from the roof area: ask how many hours of your evening load the battery will cover, on a winter evening as well as a summer one, and what happens on a cloudy day when it does not fully charge. The STC deadline is real and close. The 1 January 2027 step-down reduces certificate value for systems installed from that date, so weigh timing alongside system size, tariff, export limit and installation quality — not as a reason to rush a decision you have not made. Verify the STC values for your system with the Clean Energy Regulator's published information. Do not confuse a Western Australian project with a Queensland price. West Arthur will not directly affect Queensland wholesale prices, tariffs, or the feed-in tariff paid to a Brisbane household. Its relevance is indirect: it shows where storage duration is heading. The direct questions for your home are local.
What this means for Queensland and Brisbane buyers
For Brisbane homeowners, the local questions are: what does Energex approve for your address, what is your export limit, what tariff are you on, and how many hours of evening load will the battery cover? For Queensland commercial buyers, verify the DNSP, tariff and export limit for your site — Energex or Ergon Energy conditions differ — and watch how longer-duration storage changes the evening price shape. For Queensland's grid as coal plants retire, long-duration storage needs will grow, because the grid will need firm power for longer stretches when solar and wind are low. That is a general statement, not a claim about a particular Queensland project; Queensland will need its own answers, at its own scale, involving a mix of storage durations, transmission and other firming, and this blog does not state what that mix should be. For Queensland investors and developers, the lesson is about process and sizing: a Queensland project will face its own state and federal assessments, and a developer who treats a referral as an approval, or a Priority List place as a guarantee, is making an error that an independent technical review would catch.
What EServices4U would check independently
The same discipline that applies to a 500 MW project applies, at a smaller scale, to any Queensland solar, battery or tender decision. The approval and connection: verify the connection approval, approved inverter capacity, export limit, and whether the connection is basic or negotiated — with Energex or Ergon Energy, as applicable — before relying on any generation or export figure. The sizing against the real load: model generation against the load shape, hour by hour and season by season, rather than sizing from roof area or headline capacity. A battery's value depends on duration as well as power, and on the tariff and export limit for the site. The contract and the figures: read the tender, quote or power purchase agreement terms — price and indexation, term, volume and shape, delay and underperformance provisions, curtailment risk — and test every saving, price or payback figure before relying on it. The standards and certificates: verify STC values and eligibility, including the 1 January 2027 step-down and the mid-scale application status, against the Clean Energy Regulator's published information.
Frequently asked questions
What was referred on 13 November 2026?
West Arthur Energy referred the West Arthur Wind Farm and Battery Energy Storage System — up to 92 turbines (500 MW as listed) and a battery of up to 500 MW / 4,000 MWh — under the EPBC Act. It was reported on 14 November 2026. Federal approval has not yet been obtained.
How big is the battery, and why did it double?
Up to 500 MW / 4,000 MWh, about eight hours at rated power. When lodged with the local council in October 2026 it was up to 500 MW / 2,000 MWh; the 13 November referral doubles the stored energy to 4,000 MWh. The referral does not state a single reason for the change, and this blog does not invent one.
Where is the project, and how big is its footprint?
In the Shire of West Arthur, Western Australia, about 3 km south of Darkan and about 40 km east of Collie. The total development footprint is about 10,996.76 hectares; actual construction disturbance is about 564.75 hectares, mostly previously developed agricultural land, with no more than 5.67 hectares of native vegetation clearing plus about 0.61 hectares of scattered farmland trees.
Is the project approved, financed or under construction?
No. It is early stage: a state submission to the Western Australian EPA on 15 October 2026, a state comment period from 26 October to 1 November 2026, and a federal EPBC referral on 13 November 2026. The developer estimates construction of two to three years, commencement in July 2027 and first power in 2030, but those are estimates, not confirmed dates.
What is the National Renewable Energy Priority List?
It provides approval coordination support only. It is not an approval and does not guarantee one.
What are the environmental issues?
Surveys identified potential habitat and foraging areas for the protected black cockatoo. The scheme proposes to control impacts through turbine layout adjustment, limited vegetation clearing, and an adaptive management plan for birds and bats. Whether the project is likely to have a significant impact on matters of national environmental significance is the question the federal review must answer.
What does an eight-hour battery mean for Queensland buyers?
It shows where storage is heading: longer duration, able to cover the evening peak and the night, not just two hours. For Queensland homeowners and businesses, the practical lesson is to size a battery from the load shape and to verify the tariff, export limit and connection approval — Energex in South East Queensland, Ergon Energy regionally — before signing. West Arthur connects to the SWIS, not the NEM, so it will not directly change Queensland prices.
What should I watch next?
The federal controlled-action decision and level of assessment, the state EPA assessment, the Clean Energy Link-East transmission timing, financing, and turbine and battery procurement. Verify the current status of each milestone before relying on any date, including the STC step-down on 1 January 2027 and the Clean Energy Regulator's mid-scale application opening, expected in mid-to-late November 2026.
Get an independent check before you sign
The West Arthur referral is a useful benchmark for how large energy projects are now proposed: bigger turbines, longer storage, and a referral that asks the federal government to assess the environmental impact before anything is built. It is also a reminder that the most important sentence in any renewables announcement is often the one about what has not happened yet — no approval granted, no financing secured, no construction started. For a Queensland business or homeowner, the checks are the same: verify the connection approval, model the sizing against your real load, read the contract, and test every figure before you rely on it.
EServices4U provides independent solar and electrical engineering advice for Queensland and Australian businesses, developers and homeowners. We do not sell solar installations and we do not receive installer commissions, so our reviews are independent of any tenderer or developer. We are based in Queensland and serve clients Australia-wide. Learn more on the EServices4U home page, see packages and pricing, read about Owner's Engineer services, and meet the team.
Start with a free 15-minute consultation to talk through your tender, system, building, or project and find out which fixed-fee review fits, if any. Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. No obligation, and it does not include a written report.
Residential quote review — from $149: a fixed-fee independent review of a residential solar or battery quote, for homeowners who want the same rigour applied to a home system. See packages and pricing.
Solar & battery feasibility — from $299: an independent assessment of whether solar and batteries suit your site, including load-shape, tariff and export considerations, before you go to tender.
Home Owner's Engineer — from $599: independent engineering support for a residential project, from design review through to installation checks. See Owner's Engineer services.
Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off — from $495: an independent commercial assessment, including single-line diagram review and sign-off where applicable, for commercial and industrial projects. See packages and pricing and meet the team.
To start, visit the EServices4U home page or request a quote review, or call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. Bring your tender, your quote, or your connection approval — an independent check before signing is the cheapest insurance you can buy.





Comments