Brisbane Apartment Solar for Your Own Unit: Shared Roofs, Shared Solar and What Your Body Corporate Can and Cannot Block
If you own an apartment in Brisbane, you probably already know the frustrating part of solar. You can see the roof from your balcony and feel the Queensland sun on it all day, yet the panels are not yours to put up. The roof belongs to everyone at once — or, more precisely, to the body corporate on behalf of all lot owners.
This guide is for the individual apartment or unit owner who wants solar for their own lot, not for the common areas. It is not about the body corporate buying a system for the lifts, pool pump or car park lights. That is a different job, with a different decision and budget, and it was covered in the earlier guide for committees, "Brisbane Strata Solar: Common Property Guide for Committees" (30 October 2026). It is also distinct from the townhouse guide of 9 November 2026, which dealt with an own roof or a shared roof across two or three lots. This guide is about your unit: your panels, your inverter, your meter and your bill, on a roof you share with your neighbours.
The short answer is encouraging, with a condition. In Queensland, a body corporate generally cannot simply prohibit solar on a unit in a class 2 apartment building. Since 1 January 2010, covenants and by-laws have not been able to prohibit solar photovoltaic (PV) systems or solar hot water systems, under Chapter 8A, part 2 of the Building Act 1975 (Qld), as published by Business Queensland. Amendments in 2022, in effect from 10 June 2022, treat class 1 buildings (houses and townhouses) and class 2 buildings (apartments and units) differently, and for class 2 buildings the rules are more specific — and more favourable to owners than many committees realise.

Who this guide is for — and who it is not for
This guide is for you if you own a lot in a Brisbane apartment or unit complex and you want solar that serves your lot. You might be an owner-occupier who works from home and runs the air conditioning through the middle of the day. You might be a landlord who wants to make the unit more attractive to tenants and reduce the tenant's daytime grid use. You might be one of several owners who each want their own share of the roof, rather than waiting for the body corporate to act on common-area solar.
How apartment roofs are owned in Queensland
Most Queensland apartment buildings are on a building format plan (BFP). Under a building format plan, the lot boundaries are generally the walls, floors and ceilings of the unit itself, and everything outside those boundaries — including the roof, external walls, stairwells, lifts and common areas — is common property owned by the body corporate on behalf of all lot owners. Putting panels on the roof is therefore putting something on common property, even if the panels only serve your unit. That is why consent, allocation and conditions matter: you are asking to use a shared asset for a private benefit, and the other owners have a legitimate interest in how that is done fairly.
A smaller number of Queensland buildings are on a standard format plan. Under a standard format plan, lot boundaries are generally measured on the ground, and the lot can include the land and the building on it — including, in some townhouse and duplex-style developments, the roof above that lot. In that case the roof above your lot may be yours, not common property, and the approval path is different. This is more common for townhouses and duplexes than for multi-storey apartment blocks, but it does occur, and it is worth checking before you assume the roof is common property.
The three routes to solar for your own unit
Route | How it works | Best suited to | Main trade-off |
1. Dedicated panels + own inverter and meter | Your own panels on an allocated part of the roof, wired to your own inverter and meter | Buildings with enough roof space for each participating lot; owners who want full control | Needs an agreed roof allocation and a cable route to your unit; harder in tall buildings |
2. Shared solar / SolShare-style allocation | One shared array, with each unit's share allocated electronically to its own meter | Buildings where individual cable runs are impractical; many owners want solar at once | Needs a shared-system agreement, a special resolution and a clear exit and transfer rule |
3. Embedded network | A private network inside the building buys and sells power to lots, often with central solar and batteries | Larger complexes; buildings already considering an embedded network | Most complex legally and commercially; needs careful review of contracts and consumer protections |
Route 1 is the simplest to understand, and the hardest to install in a tall building. Your panels sit on your allocated patch of roof. A cable runs from those panels — usually via a riser, conduit or cable tray — down to your inverter, typically near your meter board, on your balcony or in a service area, and then to your meter. The solar you generate offsets your own consumption first, and any excess is exported to the grid through your meter, subject to your network export limit. You own the system, you maintain it, and you can see exactly what it produced on your inverter app or meter data.
Route 2 is shared solar, and it is the route most Brisbane apartment owners will hear about first. In a shared solar arrangement, one array is installed on the roof — often a larger, better-optimised array than any single unit could justify on its own — and the output is allocated electronically between the participating units. Each unit still has its own meter and its own bill, but the solar share assigned to that unit reduces the grid power it needs to buy. The best-known Australian technology for this is SolShare, made by Allume Energy, which allocates solar from a single shared array to multiple units behind their existing meters.
Allume Energy's published guide reports that SolShare is installed in more than 13,000 apartments, including a Queensland complex — a manufacturer-published figure, read in November 2026. The same guide gives indicative system sizes of around 22 kW and 29.26 kW serving 15 single-phase units or 5 three-phase units. Those are published guide figures, not a promise for your building: the right size depends on your roof, your units' loads, your network approval and your budget. Treat them as a sense of scale — a shared system is typically a whole-building-sized array, not a single-house-sized one — and test any proposed size against your building's actual roof and load data.
Route 3 is an embedded network, and it is the most complex of the three. In an embedded network, a private network operator manages the electricity network inside the building. The building buys power in bulk from the grid, generates some of its own power from central solar (and sometimes batteries), and sells power to each lot through the embedded network. Each lot still has a meter, but the retailer relationship and billing arrangement are different from a standard grid connection.
The Queensland approval path, step by step
Step 1: Read your community management statement and by-laws before you talk to anyone about buying panels. Find out whether your building is on a building format plan or a standard format plan, whether the roof is common property, whether there is already a by-law about solar, and whether that by-law requires consent, sets conditions, or streamlines the process. Some Queensland buildings already have a solar by-law that says, in effect, any owner may install solar on the roof directly above their lot with committee consent, subject to standard conditions. If your building has one, your path is much simpler. If it does not, you may need to create one — which is a separate decision, explained below.
Step 2: Work out whether your proposal needs committee approval or a general meeting. This is where the $3,000 line matters. BC Systems guidance published in October 2023 explains that, for a lot-owner improvement to common property, a proposal costing more than $3,000 must go to owners at a general meeting, while a proposal costing under $3,000 can be approved by the committee. Most own-unit solar systems cost well over $3,000, so in practice most proposals will need a general meeting — but check the figure against your building's by-laws and the current Queensland regulation, because the threshold and process can be affected by your specific scheme. Do not assume the committee can approve a $10,000 roof installation on its own.
Step 3: If a general meeting is needed, understand the voting rules for your type of proposal. A single owner seeking consent to install their own panels on common property is generally seeking approval for a lot-owner improvement, and the meeting and voting requirements for that type of motion apply. A shared solar system — where the body corporate itself is involved in a shared array or a change to common property that affects all lots — may need a different type of resolution, and the voting threshold is higher.
For shared solar, Allume Energy's state-by-state strata solar guide, read in November 2026, sets out the Queensland position clearly. Queensland shared solar needs a special resolution at an Extraordinary General Meeting (EGM). A special resolution requires at least two-thirds of the votes cast to be in favour, votes against of not more than 25% of the total number of lots in the scheme, and lot entitlements of votes against of not more than 25% of the total lot entitlements. The meeting needs a minimum of 21 days' notice, and the quorum is 25% of eligible voters. Those are published guide figures for Queensland, and they are the numbers to check against your body corporate manager's advice and your community management statement before you call a meeting. Getting the notice period or quorum wrong can invalidate the meeting, and that is an expensive mistake to discover afterwards.
Step 4: If a new by-law is needed, treat it as a separate decision. A by-law can streamline future solar installations — for example, by saying any owner may install solar on the roof above their lot with committee consent, subject to standard conditions. Creating a by-law is itself a decision that needs a resolution, and it needs to be drafted carefully so it is fair, enforceable and consistent with Queensland law. A well-drafted solar by-law is one of the best investments a body corporate can make: it turns every future solar request from a fresh negotiation into a standard process.
Step 5: Get network approval in writing, and do not order panels before you have it. In South East Queensland the network is Energex. In regional Queensland it is Ergon Energy Network. Either way, confirm your connection approval and your export limit in writing before installation. The export limit is the maximum solar power you can send back to the grid, and it affects how much of your system is useful and how your inverter must be configured. An installer who tells you not to worry about network approval, or who proposes to install first and seek approval later, is giving you advice you should not follow.
Step 6: Install, inspect, and record. Once approval and network approval are in place, the installation should be carried out by a suitably qualified and licensed installer, in accordance with the approved layout, cable route and conditions. After installation, make sure the system is inspected and tested, the meter is correctly configured, and the records are updated: the body corporate records should note the installation, the roof allocation and the ownership, and you should keep the certificates, warranties, manuals and network approval for your own records and for a future sale.
What the body corporate CAN still control — and what it cannot block
What the body corporate cannot do is prohibit solar outright. Since 1 January 2010, covenants and by-laws have not been able to prohibit solar PV or solar hot water systems, under Chapter 8A, part 2 of the Building Act 1975 (Qld). A by-law that says "no solar panels on the roof" is not enforceable to the extent that it purports to prohibit solar. A committee that tells you solar is banned in the building is, in most cases, telling you something Queensland law does not support.
What the body corporate can do is set reasonable conditions, and it can withhold consent in limited circumstances. For class 2 buildings — apartments and units — where the roof is common property and a by-law requires consent, Business Queensland's published guidance on covenants and body corporate by-laws for sustainability explains the position after the 2022 amendments. The owner should ask for consent, but the body corporate may only withhold consent to the extent necessary to preserve the building's structural integrity, or if there is insufficient space for each other owner to also install solar on the surface. There is also a noise condition for solar hot water piping. Those are the published grounds for withholding consent for solar PV in a class 2 building. They are narrow, and they are specific — and that matters.
Beyond those two grounds, the body corporate can still control how the installation is done, even if it cannot block the installation itself. It can require that the work is carried out by a licensed installer, that the roof is protected during installation, that the system is maintained and insured, that access to the roof is managed safely, and that the system is removed or relocated if the roof needs repair. It can require the owner to pay for the installation, for any damage caused, and for reinstating the roof. It can set conditions about the inverter location, the cable route, and the hours during which work can be carried out. Those are reasonable conditions, and a good proposal will offer them before they are asked for.
Metering and billing: how your share is measured
For Route 1 — dedicated panels and your own inverter and meter — metering is straightforward. Your panels generate power, your inverter converts it, and your meter measures what you use from the grid and what you export to the grid. Your retailer bills you on the net amount, at your tariff, and pays you a feed-in tariff for exported power, subject to your export limit and your retailer's terms. You can see generation on your inverter app, consumption and export on your meter data, and your bill from your retailer. If you move out, the system stays with the unit (unless your agreement says otherwise), and the new owner or tenant takes over the meter and the system.
A note on feed-in tariffs, because they are often misunderstood. In the Energex area — South East Queensland, including Brisbane — feed-in tariffs are set by retailers, not by a regulator. The rate you are paid for exported solar depends on your retailer and your plan, and it can change. In regional Queensland, the feed-in rate is set by the Queensland Competition Authority, and the published rate from 1 July 2026 is 6.006 cents per kilowatt-hour. Do not assume a feed-in rate from a quote, a neighbour, or a website without checking it against your own retailer and your own plan. And do not size a system on the assumption that export income will be a major part of the return: for most apartments, the main benefit is the daytime solar you use yourself, not the power you export.
Sizing for an apartment: small loads, daytime use, and the battery question
Apartments are not houses, and apartment solar should not be sized like house solar. A typical Brisbane house might have a large roof, a large daytime load from a pool pump and ducted air conditioning, and a system of 6.6 kW or larger. A typical apartment has a smaller roof share, a smaller daytime load, and a different pattern of use. Sizing for an apartment starts with your actual load, not with the maximum number of panels that will fit.
For many apartments, a small system is the right system. A dedicated system of 2 kW to 4 kW may be all that a single unit needs, and all that its fair roof allocation can support. A shared system, by contrast, may be 22 kW or larger for the whole building, with each unit's share being a fraction of that total. Do not let a salesperson size your system by the roof alone, or by a standard house package. Ask for a sizing calculation based on your interval data, your daytime load, your roof allocation and your export limit — and ask to see it.
Costs, quotes and the 1 January 2027 step-down
Cost is the question every owner asks first, and it is the question this guide cannot answer with a single figure. The cost depends on system size, the route you choose, the cable run, the inverter location, roof access, any structural work, network approval, and the installer's price. A dedicated 3 kW system with a short cable run will cost very differently from a shared 29 kW system split between 15 units. Any guide that gives a single price for "apartment solar" is giving you a figure that does not apply to your building.
Get at least two comparable quotes, and make them comparable. Give each installer the same information: the roof allocation, the cable route, the inverter location, the system size you want priced, and the network export limit. Ask each one to price the same scope, in writing and itemised, with panel and inverter makes and models, warranty terms, expected generation for your roof, and assumptions about your tariff and export limit. A quote that does not state its assumptions cannot be checked — and a quote that cannot be checked should not be accepted.
The 1 January 2027 step-down is a dated change to factor into timing, without letting it rush you into a bad decision. From 1 January 2027, the solar deeming period falls from 5 years to 4 years, and the battery STC factor falls from 6.8 to 5.7, for systems up to 100 kW — published guide figures. In plain language, the small-scale technology certificate (STC) incentive that reduces the upfront cost will be worth less from 1 January 2027, because the deeming period is shorter. The exact dollar effect depends on system size, the STC price at the time, and your installer's calculation, so ask your installer to show you the STC calculation, and what it would be if installation fell after 1 January 2027. If approval and installation can realistically be completed before that date, the higher value may apply. If they cannot — and for many apartment buildings, with a general meeting to organise, they genuinely cannot — do not let a salesperson pressure you into ordering panels before approval is in place to "beat the step-down." A system installed without proper approval will cost far more than the STC difference.
South Australia's strata solar program is worth mentioning, because Brisbane owners may hear about it and assume Queensland has the same thing. It is reported that South Australia launched a $17.8 million shared solar and battery program for strata — known as StrataCharge — reported on 15 November 2026. Queensland has no equivalent program announced as at 15 November 2026, and Queensland owners cannot apply to the South Australian program. Check the Queensland Government's current rebates before you finalise a budget, because programs change, but do not budget on the assumption that a South Australian program applies in Queensland.
What to check in a quote
A good quote is a document you can check, not a sales pitch you have to trust. Look for a roof plan showing exactly which panels are yours, the inverter location and cable route, whether strata-approval help and the network application are in scope, who owns, insures and maintains the system, product, performance and workmanship warranties in years with the party honouring each one named, network approval and the export limit, and an itemised price with the STC discount shown separately. If a quote fails several of these checks, get a second quote.
The mid-scale STC opening: what changed on 17 November 2026
A dated update that matters for larger whole-building systems. The Clean Energy Regulator opened mid-scale STC applications on 17 November 2026 for solar systems over 100 kW to 1 MW installed from 1 October 2026, with a fixed 5-year deeming period. That is a published, dated change, relevant where a whole-building shared system is over 100 kW — for example, a large apartment complex where the shared array serves many units and exceeds the 100 kW small-scale threshold. For most individual owners, a dedicated system for a single unit will be well under 100 kW, and the small-scale rules and the 1 January 2027 step-down above are the ones that apply. If your building is considering a shared system, ask the installer or adviser: is the proposed system under or over 100 kW, which STC scheme applies, what deeming period applies, and what is the STC value in the quote? Do not let a quote mix the two schemes.
What EServices4U would check independently
An independent check is a review by someone who does not sell panels and does not receive installer commissions. EServices4U would check the roof allocation and shading for your patch, whether the route and sizing suit your building and daytime load, whether the approval path and ownership, maintenance and transfer agreement are correct, whether the quote is itemised and comparable with current STC figures, and whether network approval, the export limit and the metering arrangement are confirmed in writing and checkable on your bill.
How This Works for Both Sides
Good apartment solar is not a win for one owner and a loss for everyone else. It is a win for the participating owner, who gets daytime solar for their own unit, and a win for the body corporate and other owners, who get a clear, fair process, a protected roof, and a building better prepared for the next owner who wants solar.
For the participating owner | For the body corporate and other owners |
Solar for your own unit, on an agreed roof allocation, with your own meter and bill | A clear roof allocation plan, so no one owner takes the best roof and leaves nothing for others |
A system sized to your daytime load, not to a standard house package | Structural integrity protected, with evidence, and the roof reinstated after installation |
A written agreement on ownership, maintenance, insurance and removal for roof works | A by-law or agreement that turns future solar requests into a standard process, not a fresh dispute |
Network approval and export limit confirmed in writing before installation | No cost to non-participating owners, unless the body corporate agrees to share a cost for a shared benefit |
A quote you can check, with the STC calculation and generation figure shown | Records updated, so a future buyer, tenant or committee can see what was installed and who owns it |
Frequently asked questions
Can my body corporate stop me putting solar on my apartment roof?
In most cases, no — not outright. Since 1 January 2010, covenants and by-laws have not been able to prohibit solar PV or solar hot water, under Chapter 8A, part 2 of the Building Act 1975 (Qld). For a class 2 building where the roof is common property and a by-law requires consent, the body corporate may only withhold consent to the extent necessary to preserve structural integrity, or if there is insufficient space for each other owner to also install solar. It can still set reasonable conditions, and you still need to follow the correct approval process.
Do I need a special resolution for my own panels?
It depends on what you are proposing. A single owner seeking consent for their own dedicated panels is generally seeking approval for a lot-owner improvement, which for a system costing over $3,000 will generally mean a general meeting. A shared solar system needs a special resolution at an Extraordinary General Meeting in Queensland, with at least two-thirds of votes cast in favour, votes against of not more than 25% of total lots, and lot entitlements of votes against of not more than 25% of total entitlements, with a minimum of 21 days' notice and a quorum of 25% of eligible voters — published guide figures from Allume Energy, read in November 2026.
What is the difference between dedicated panels and shared solar?
Dedicated panels are yours alone: your panels on your allocated patch, wired to your own inverter and meter. Shared solar is one array shared between several units, with each unit's share allocated electronically to its meter. Dedicated solar suits buildings with enough roof space and a workable cable route. Shared solar suits taller buildings, buildings where many owners want solar at once, and buildings where one optimised array uses the roof better than many small patches.
How much solar do I need for an apartment?
Less than a house, in most cases — but the right size depends on your daytime use. Start with your interval meter data or bills, and work out how much power you use between 9 am and 4 pm. For many apartments, a dedicated system of 2 kW to 4 kW is the right size. Do not size by the roof alone, and do not accept a standard house package without a sizing calculation based on your load, roof allocation and export limit.
Do I need a battery with apartment solar?
Usually not as a first step. A battery stores daytime solar for evening use, but it adds cost, needs space and a suitable location, and must be considered against the body corporate's rules and fire-safety requirements. For many apartments, the right sequence is solar first, review the bills for a few months, and then consider a battery if the data shows a meaningful amount of solar is being exported. Ask for the battery calculation separately, with your load data, tariff and export limit.
What happens to my solar if I sell my apartment?
That depends on your agreement — which is why it needs to be in writing before installation. In most dedicated arrangements, the system stays with the unit and transfers to the new owner. In a shared arrangement, the share should transfer to the new owner, or revert to the pool, according to the shared solar agreement. Make sure the agreement answers this question, and that the body corporate records and the sale contract reflect it.
What if I am a tenant, not an owner?
A tenant cannot approve a roof installation, but a tenant can ask the owner to consider it. Talk to your owner, put the request in writing, and attach the information in this guide. If the owner installs solar, talk to the owner about how it will work — whether your tariff or retailer needs to change, how daytime solar will affect your bill, and whether the lease needs to reflect it.
Is there a Queensland government rebate for strata solar?
Not an equivalent to South Australia's program, as at 15 November 2026. It is reported that South Australia launched a $17.8 million shared solar and battery program for strata, known as StrataCharge, reported on 15 November 2026. Queensland has no equivalent program announced as at that date, and Queensland owners cannot apply to the South Australian program. Check the Queensland Government's current rebates before you finalise a budget, because programs change.
Will the 1 January 2027 STC step-down affect me?
It may, if your system is installed after 1 January 2027. From that date, the solar deeming period falls from 5 years to 4 years, and the battery STC factor falls from 6.8 to 5.7, for systems up to 100 kW — published guide figures. Ask your installer to show you the STC calculation for your system, and what it would be if installation fell after 1 January 2027. Do not let the step-down pressure you into ordering panels before body corporate and network approval are in place.
What if my building's roof is too small for everyone?
Then the allocation needs to be fair, and shared solar may be the better route. If the roof cannot give every lot a dedicated patch, a single shared array — optimised for the roof, with shares allocated by agreement — can serve more owners than individual patches. Ask for a roof plan showing the total area, the area already used, and the area each lot would need, and ask whether a shared system could serve more owners.
What to do next
If you own a Brisbane apartment and you want solar for your own unit, the next step is not to order panels — it is to get the information that lets you make a good decision. Read your community management statement and by-laws. Find out whether your building is on a building format plan or a standard format plan. Talk to the committee early, and ask what process it wants you to follow. Get a preliminary technical view of the roof. And get an independent check of any quote before you sign it.
Start with a free 15-minute consultation to talk through your tender, system, building, or project and find out which fixed-fee review fits, if any. Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. No obligation, and it does not include a written report.
Residential solar quote review from $149 — for a quote you have already received, checked independently before you sign. See packages and pricing.
Solar and battery feasibility assessment from $299 — to test whether solar, and whether a battery, is feasible for your unit and your building. See packages and pricing.
Home Owner's Engineer from $599 — for a larger or more complex project, with independent engineering support through the process. See owners engineer.
Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off from $495 — for a building-wide or commercial-scale proposal that needs an engineering review. See packages and pricing.
Get a quote for a review — if you are not sure which service fits, use the quote page or the free consultation above, and EServices4U will help you work out which fixed-fee review, if any, is right for your building.
EServices4U is based in Queensland and serves clients Australia-wide. You can read more about the business at EServices4U and about the people behind it on the team page. The advice is independent: EServices4U does not sell solar installations and does not receive installer commissions, so the check is of your proposal, not a sales pitch for a system.
Bring your documents to the consultation if you can. Your community management statement, your by-laws, any quote you have received, your recent bills or interval data, and any correspondence with the committee or the body corporate manager will all help. The more complete the information, the more useful the consultation will be — and the sooner you will know whether solar for your own unit is feasible, what route suits your building, and what to do next.





Comments