CER Record 5 GW FID: What It Means for Queensland Buyers

11 minutes ago
22 min read

The headline, in one paragraph: On 26 November 2026, the Clean Energy Regulator published its Q3 2026 Quarterly Carbon Market Report, and the numbers in it set a new record. A record 5 GW of large-scale renewable energy generation had reached final investment decision — FID — in the first nine months of 2026, already more than the full-year record of 4.9 GW set in 2025. By mid-November, the year-to-date total had moved again, to 5.5 GW. The Regulator responded by lifting the lower end of its 2026–2027 FID projection from 6–8 GW to 8–16 GW. At the same time, large-scale batteries were setting prices in almost half of all National Electricity Market dispatch intervals, wholesale prices were 27% lower than in the same quarter a year earlier, and rooftop solar had its strongest September quarter on record.


Why Queensland buyers should read past the headline: Two of the five Capacity Investment Scheme-supported projects that reached FID in the September quarter were Queensland solar farms — the 150 MW Ganymirra Solar Power Station and the 150 MW Majors Creek Solar Farm. Queensland also appears in the battery story, with the 1,215 MWh Stage 3 South Pine Supernode battery energy storage system among the large batteries reaching FID. That does not mean every Queensland household or business will see the same benefit, at the same time, or in the same way. Wholesale prices are not retail bills. A final investment decision is not a completed project. And an approvals pipeline that the Regulator itself describes as "subdued" is a real constraint on what comes next. This blog works through the record, figure by figure, and then asks the practical question: what does it change for an investor, a commercial or industrial buyer, and a homeowner in Queensland and Brisbane?


What FID means, in plain English: A final investment decision is the point at which a project's owners commit the money and proceed to build. It is further along than an announcement, a feasibility study, or a planning application. It is not the same as construction starting, and it is not the same as the project generating power. That distinction matters throughout this blog. When the Regulator counts 5 GW reaching FID, it is counting committed investment, not 5 GW of new power already on the grid.


Large-scale Queensland solar farm with rows of solar panels and battery storage containers under a clear sky

What happened on 26 November 2026

The publication: The Clean Energy Regulator published its Q3 2026 Quarterly Carbon Market Report — the QCMR — on 26 November 2026. The QCMR is the Regulator's quarterly account of carbon markets and renewable energy investment in Australia. It is reported that the latest edition covers the July to September 2026 quarter, with some figures updated to mid-November 2026.


The central finding: A record 5 GW of large-scale renewable energy investment reached final investment decision to the end of Q3 2026. That total already exceeded the 2025 full-year record of 4.9 GW, with a full quarter of the year still to run at the end of September. It is reported that by mid-November 2026, further investment decisions had taken the year-to-date total to 5.5 GW.


The Regulator's response: The Clean Energy Regulator raised the lower bound of its 2026–2027 FID projection from 6–8 GW to 8–16 GW. In the Q4 2025 QCMR, the Regulator had projected between 6 and 16 GW of large-scale renewable generation capacity would reach FID over 2026 and 2027. It is reported that the Q3 2026 QCMR says: "The record level of investment activity observed during 2026 has significantly reduced downside risks to this outlook." In plain terms, the Regulator is now more confident that the lower end of its earlier range will be met, because so much investment has already been committed in 2026. The upper end of the range, 16 GW, is unchanged. This blog does not treat the revised projection as a forecast that 8–16 GW will certainly be reached. It is a projection, and the Regulator's own approvals figures — set out below — show why the path from investment decision to operating project still has steps in it.


Who is involved: The Clean Energy Regulator is the publisher and the source of the investment, approvals, rooftop solar and home battery figures. The Australian Energy Market Operator — AEMO — is the source, as cited in the QCMR, of the market figures on battery discharge, price-setting and wholesale prices. The federal Capacity Investment Scheme — the CIS — is the support mechanism behind five of the nine projects that reached FID in Q3 2026, including the two Queensland solar projects named in this blog. The Australian Renewable Energy Agency — ARENA — is cited in the QCMR for its Ultra Low-cost Solar white paper on cutting deployment costs. No individual project developer is the subject of this story. The story is the market-wide data, and the Queensland projects are named because the QCMR names them.


When the underlying activity happened: The September quarter is July to September 2026. The 5 GW total is the cumulative total for the first three quarters of 2026. The 5.5 GW figure is the year-to-date total as at mid-November 2026, after the end of the September quarter. The rooftop solar and home battery figures are also to the end of Q3 2026, and the approvals figures are as at 30 September 2026. Keeping those dates straight matters, because a reader who mixes up the September quarter, the year to September, and the mid-November update will overstate or understate the record.


The record in numbers

Start with the totals, then the parts: The 5 GW record is the sum of many individual decisions. The September quarter alone contributed 2.1 GW across nine projects. That quarter matched the highest quarterly figure on record, it is reported. The split inside that 2.1 GW is what makes the quarter distinctive: solar contributed 1 GW and wind contributed 1.1 GW. Solar had its fourth-strongest quarter. Wind had its strongest quarter since tracking began. Neither fuel did this alone. Both moved in the same quarter.


Solar, in detail: Solar accounted for 1 GW reaching FID in Q3 2026, the fourth-strongest quarter for solar. Solar accounted for 3.5 GW of FID in 2026 to date. It is reported that the 3.5 GW solar total is about 30% above the previous full-year solar FID record, and that solar FID in Q2 2026 was 2 GW, before easing to 1 GW in Q3. That quarter-to-quarter movement is normal for large projects: individual large projects move in and out of the financing pipeline, so a single quarter's solar figure can fall while the annual total still sets a record. The right comparison is the annual one — 3.5 GW in nine months, already well past the previous annual record for solar. It is also reported that the 2.1 GW that reached FID in the September quarter was enough to power around 1.2 million homes.


Wind, in detail: Wind had its strongest quarter ever since tracking began, with 1.1 GW reaching FID in Q3 2026. That is more than half of the 2.1 GW quarterly total. The QCMR does not, in the reporting checked for this blog, name the individual wind projects that made up that 1.1 GW in the same way it names the Queensland solar projects, and this blog does not fill that gap with names from elsewhere. What is confirmed is the total, the record status, and the fact that wind, not solar, was the larger contributor in the September quarter itself.


The Capacity Investment Scheme: More than half of the projects reaching FID to the end of Q3 2026 were backed by the federal Capacity Investment Scheme, it is reported, demonstrating what the QCMR describes as the scheme's growing influence on the investment pipeline. In Q3 alone, five of the nine projects that reached FID received support under the CIS. The two Queensland solar projects named in the QCMR — Ganymirra and Majors Creek — were among those five. This blog does not speculate on why any individual project reached FID, or on what the CIS terms were for any individual project. Those terms and costs are not in the QCMR reporting checked for this blog, and they are not stated here.


The facts table

Item

Figure

Period / date

Source as reported

Large-scale renewable generation reaching FID, 2026 to date

5 GW — record, above 2025 full-year record of 4.9 GW

To end of Q3 2026 (30 September 2026)

Clean Energy Regulator, Q3 2026 QCMR, published 26 Nov 2026

Large-scale renewable generation reaching FID, updated year-to-date

5.5 GW

Mid-November 2026

Clean Energy Regulator, Q3 2026 QCMR, published 26 Nov 2026

Large-scale renewable generation reaching FID in Q3 2026

2.1 GW across nine projects

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

CER 2026–2027 FID projection, revised

8–16 GW, lower bound raised from 6–8 GW

Published 26 Nov 2026

Clean Energy Regulator, Q3 2026 QCMR

Solar reaching FID in Q3 2026

1 GW, fourth-strongest quarter for solar

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

Solar reaching FID in 2026 to date

3.5 GW

To end of Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Wind reaching FID in Q3 2026

1.1 GW, strongest quarter since tracking began

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

CIS-supported projects reaching FID in Q3 2026

Five of nine projects

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

Ganymirra Solar Power Station, Queensland

150 MW, CIS-supported, reached FID in Q3 2026

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

Majors Creek Solar Farm, Queensland

150 MW, CIS-supported, reached FID in Q3 2026

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

Large-scale batteries reaching FID in Q3 2026

3.4 GW and 13.8 GWh

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR, new battery pipeline tracker

Large-scale batteries reaching FID in 2026 to date

5.1 GW and 20 GWh

To end of Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Average large-scale battery capacity

More than doubled, from 265 MWh in 2025 to 621 MWh in 2026 so far

2025 compared with 2026 to end of Q3

Clean Energy Regulator, Q3 2026 QCMR

Richmond Valley Solar Farm BESS, New South Wales

2,200 MWh, reached FID

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Baranduda Electrical Energy Reserve, Victoria

1,860 MWh, reached FID

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Moorabool Battery, Victoria

1,200 MWh, reached FID

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Stage 3 South Pine Supernode BESS, Queensland

1,215 MWh, CIS-supported, reached FID

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Koolunga BESS, South Australia

800 MWh, CIS-supported, reached FID

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Large-scale batteries setting NEM prices

Record 48% of dispatch intervals

Q3 2026

AEMO, as cited in the QCMR

Average large-scale battery discharge

More than tripled year-on-year

Q3 2026 compared with Q3 2025

AEMO, as cited in the QCMR

Evening-peak generation, batteries compared with gas

Batteries 8%, gas 1.5%, first time in any quarter

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR, citing AEMO

Economic offloading of solar

Fell 54% year-on-year

Q3 2026 compared with Q3 2025

Clean Energy Regulator, Q3 2026 QCMR

NEM wholesale electricity prices

Fell 27% compared with Q3 2025

Q3 2026

Clean Energy Regulator, Q3 2026 QCMR, citing AEMO

Rooftop solar installed in the September quarter

890 MW, strongest September quarter on record

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

Rooftop solar installed in 2026 to date

2.8 GW, on track for a new annual record above 3.2 GW

To end of Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Behind-the-meter battery capacity, installed and approved

10.3 GWh in total

To end of Q3 2026

Clean Energy Regulator, Q3 2026 QCMR, as reported

LRET approvals in Q3 2026

0.6 GW, described as "subdued"

July–September 2026

Clean Energy Regulator, Q3 2026 QCMR

LRET approvals in 2026 to date

2.1 GW

To end of Q3 2026

Clean Energy Regulator, Q3 2026 QCMR

Capacity under assessment for LRET approval

570 MW

As at 30 September 2026

Clean Energy Regulator, Q3 2026 QCMR

CER 2026 approvals projection, revised down

2.6–3.4 GW, down from 3.5–4.5 GW

Published 26 Nov 2026

Clean Energy Regulator, Q3 2026 QCMR

Mid-scale SRES applications

Opened in the REC Registry for systems over 100 kW to 1 MW installed on or after 1 October 2026

Opened 17 November 2026

Clean Energy Regulator bulletin, 17 Nov 2026


Queensland in the September quarter: Ganymirra and Majors Creek

What is confirmed: Two Queensland solar projects reached FID in Q3 2026 and received support under the Capacity Investment Scheme: the 150 MW Ganymirra Solar Power Station and the 150 MW Majors Creek Solar Farm. Together they account for 300 MW of the 1 GW of solar that reached FID in the quarter, and 300 MW of the 2.1 GW total across all fuels. That is a material Queensland share of a national record quarter, and it is the reason this blog leads with Queensland rather than treating the state as a footnote to a national story.


Batteries: the other record inside the record

A new tracker, and a very large quarter: The Clean Energy Regulator's new large-scale battery pipeline tracker recorded 3.4 GW and 13.8 GWh of storage capacity reaching FID in Q3 2026. That took the 2026 total to date to 5.1 GW and 20 GWh. The Q3 battery figure alone — 13.8 GWh — is more than two-thirds of the full-year-to-date total of 20 GWh. The quarter was not a small addition to a steady trend. It was the quarter that made the year.


Bigger batteries, not just more batteries: The average capacity of large-scale batteries more than doubled, from 265 MWh in 2025 to 621 MWh in 2026 so far. That is a change in the size of the typical project, not only in the number of projects. A 621 MWh battery can store and discharge far more energy than a 265 MWh battery of the same power rating, and it can sustain its output for longer. The QCMR does not, in the reporting checked for this blog, give a single reason for the increase in average size, and this blog does not invent one. What can be said, from the figures themselves, is that developers are committing to larger storage durations, and that the pipeline is shifting towards projects that can cover more of the evening peak rather than only a short burst at the start of it.


The named projects: The projects to reach FID in Q3 included the 2,200 MWh Richmond Valley Solar Farm battery energy storage system in New South Wales, the 1,860 MWh Baranduda Electrical Energy Reserve and the 1,200 MWh Moorabool Battery, both in Victoria. In Queensland, the 1,215 MWh Stage 3 South Pine Supernode battery energy storage system, supported by the CIS, reached FID. The 800 MWh Koolunga battery energy storage system, also supported by the CIS, is in South Australia — not Queensland — and this blog places it there deliberately, because the sentence in the source reporting that names Supernode and Koolunga together is easy to misread as placing both in Queensland.


What changed in the market in Q3 2026

Batteries setting the price: The QCMR cites the Australian Energy Market Operator as reporting that average large-scale battery discharge more than tripled year-on-year, and that large-scale batteries set prices in a record 48% of National Electricity Market dispatch intervals in Q3 2026. A dispatch interval is the short period — five minutes in the NEM — for which the market is dispatched and priced. To say batteries set the price in 48% of intervals is to say that, in almost half of all five-minute periods in the quarter, the marginal unit setting the price was a battery, charging or discharging. That is a record, and a substantial change from a market in which batteries were a small participant. It does not mean batteries supplied 48% of all electricity in the quarter. Price-setting and energy supplied are different measures. A battery can set the price in an interval in which it supplies only a small share of total energy. The 48% figure is about influence on price, not about share of generation.


Batteries overtaking gas in the evening peak: The QCMR reports that batteries supplied more evening-peak generation — 8% — than gas — 1.5% — for the first time in any quarter. The evening peak is the period when households return home, lights and appliances switch on, air conditioning load is high, and solar output has fallen away. It has historically been the most expensive and most gas-dependent part of the day. For batteries to supply more evening-peak generation than gas in a whole quarter is therefore a notable change in how the evening peak is met. It is reported that the same passage links this to fewer negative-price intervals, so more available large-scale solar generation was used. The logic, as reported, is that batteries charge when prices are low or negative during the day, store that energy, and discharge it in the evening — reducing the amount of solar generation that has to be curtailed or economically offloaded, and reducing the call on gas in the evening.


Less solar wasted: The share of available solar generation reduced by solar farms in response to low prices — economic offloading — fell by 54% year-on-year. Economic offloading is not the same as a solar farm being switched off for a technical fault. It is a commercial decision: when prices are very low or negative, a solar farm reduces its output because generating at that price loses money. A 54% fall means far less solar generation was held back for price reasons than in the same quarter a year earlier. The QCMR, as reported, connects that fall to battery participation and to fewer negative-price intervals. Batteries give daytime solar energy somewhere to go. That is the mechanism, as reported. This blog does not add a second mechanism of its own.


Wholesale prices fell 27%: National Electricity Market wholesale electricity prices fell 27% compared with Q3 2025, with battery participation and lower grid demand cited as contributors. It is also reported, from AEMO's Quarterly Energy Dynamics Q3 2026, that the average wholesale spot price across the NEM was $63 per MWh in the quarter, the lowest September-quarter average since 2021. That $63 figure is an average across the NEM for the quarter. It is not a Queensland price, it is not a retail price, and it is not a promise about any individual bill. Wholesale prices are one component of a retail bill, alongside network charges, retail costs and margins, and other charges. A 27% fall in wholesale prices does not translate into a 27% fall in any household or business bill, and this blog does not suggest that it does. What the fall does show, on the QCMR's own terms, is that the market outcome in Q3 2026 was materially cheaper at the wholesale level than in Q3 2025, and that battery participation and lower grid demand were cited as contributors.


Why it happened, and what it changes

The Capacity Investment Scheme's role: More than half of the projects reaching FID to the end of Q3 2026 were backed by the CIS, it is reported. In Q3, five of nine projects had CIS support. The CIS is a federal scheme that underwrites revenue for large-scale renewable generation and storage, reducing the revenue risk that can otherwise stop a project from reaching FID. This blog does not describe the CIS contract terms for any individual project, because those terms are not in the QCMR reporting checked for this blog. What can be said, from the QCMR figures, is that CIS-backed projects were a majority of the FID total to the end of Q3, and that the scheme's influence on the pipeline is growing, in the QCMR's own assessment. A reader who wants to understand whether a particular project would have reached FID without CIS support will not find that counterfactual in the QCMR, and this blog does not attempt it.


Cheaper deployment, as cited by ARENA: The QCMR cites ARENA's Ultra Low-cost Solar white paper as identifying opportunities to cut deployment costs, including improved cell and module efficiency, innovation in construction and deployment models, automation, prefabrication, modular delivery, and digital and data-driven operational and maintenance optimisation. Those are pathways, not realised savings. The white paper identifies where costs could fall. It does not state that they have already fallen by a given amount, and this blog does not convert a list of opportunities into a cost-reduction figure. The relevance for a buyer is different: if deployment costs do fall through efficiency, automation and prefabrication, the economics of future projects improve. That is a direction of travel, not a price.


The approvals lag: the part of the report that points the other way

"Subdued" is the Regulator's word: Approvals of renewable generation projects under the Large-scale Renewable Energy Target were "subdued" in Q3 2026, the QCMR says, and it adds that approvals are expected to lag the recent uplift in investment. That expectation is important. It means the Regulator is not surprised that approvals are lower than FID. An investment decision and an LRET approval are different steps, taken at different times, by different processes. A project can reach FID before its LRET approval is finalised, and the approval can follow. The lag is therefore not, on the QCMR's own terms, a contradiction of the record. It is a sequencing fact.


The figures: A total of 0.6 GW was approved in Q3 2026, bringing approvals to 2.1 GW for the year to date. With 570 MW under assessment as at 30 September 2026, the Regulator revised its 2026 approvals projection down from 3.5–4.5 GW to 2.6–3.4 GW. That is a cut of roughly 0.9–1.1 GW at each end of the range. It is a material downgrade, and it sits in the same report as the upgrade to the FID projection. The two revisions point in opposite directions for a reason: investment decisions are running ahead of approvals.


Why it matters for the record: If approvals stay subdued while FID stays strong, the question for 2027 is not whether investment can be committed, but whether committed projects can move through approval and connection in good order. This blog does not predict that outcome. It notes the tension the QCMR itself presents: a record FID year, a raised FID projection, a lowered approvals projection, and a small under-assessment total. A reader who cites only the 5 GW figure, without the 0.6 GW approvals figure, is telling half the story. A reader who cites only the approvals cut, without the 5 GW record, is telling the other half. Both figures are in the same report, published on the same day, and both belong in any honest account of it.


Rooftop solar and home batteries: the household side of the same quarter

Rooftop solar's strongest September quarter: Rooftop solar recorded its strongest September quarter on record, with 890 MW installed, taking total 2026 installations to 2.8 GW — and putting the year on track to set a new annual record of higher than 3.2 GW. It is also reported that rooftop solar added 90,042 installations in the September quarter alongside that capacity figure. The year-to-date total of 2.8 GW almost matches the whole of 2025, with three months still to go at the end of September. Q2 2026 was the biggest rooftop solar capacity quarter on record at 1 GW, it is reported, which puts the Q3 figure of 890 MW in context: Q3 was a record September quarter, not a record quarter overall.


Home batteries: 10.3 GWh: Home battery installations remained strong, the Regulator says, with a total of 10.3 GWh of behind-the-meter capacity installed and approved under the Cheaper Home Batteries Program in 2026 to the end of Q3. That is a capacity figure, not a household count. It is reported that the growth trajectory has led the Regulator to increase its full-year projection for behind-the-meter battery capacity from 8–12 GWh to 13–15.5 GWh. That is a substantial upward revision, and it is consistent with the large-scale battery story: storage, at both grid scale and household scale, is growing faster than the Regulator had projected earlier in the year. This blog does not convert 10.3 GWh into a number of homes, because the QCMR reporting checked does not give that conversion, and the average battery size per home varies too much for an invented average to be honest.


The mid-scale opening — a coming boost: The QCMR notes that the rooftop and battery figures are in line for a further boost from the launch of applications for the mid-scale Small-scale Renewable Energy Scheme incentive, which brings rooftop systems from 100 kW to 1 MW into the scheme. Applications for small-scale technology certificates for mid-scale systems opened in the REC Registry on 17 November 2026, according to the Clean Energy Regulator's bulletin of that date. The regulations were amended in October 2026, expanding eligibility for solar PV systems under the SRES from 100 kW to 1 MW. The change applies to mid-scale systems installed on or after 1 October 2026. That timing matters: a system installed in October, before applications opened, can still be eligible, because eligibility turns on the installation date, not the application opening date. A commercial buyer in Queensland with a roof in the 100 kW to 1 MW band — a warehouse, a school, a shopping centre, a food processor, a farm shed, a council building — is the buyer most directly affected. That buyer could not previously create STCs for a system above 100 kW under the SRES. From 1 October 2026, they can, subject to the scheme's requirements. This blog does not state a dollar value for that support for any particular system size, because the value depends on the system size, the zone rating, the deeming period, and the certificate price at the time.


The 1 January 2027 step-down — read this before you sign: The STC deeming period falls from five years to four years on 1 January 2027, and the battery STC factor falls from 6.8 to 5.7 per usable kWh on the same day. That is a scheduled step-down, published by the Clean Energy Regulator, not a sales deadline invented by a retailer. For solar, a system installed in 2026 is deemed for five years; the same system installed in 2027 is deemed for four years, so it earns about 20% fewer certificates, before rounding. For batteries, the factor fall from 6.8 to 5.7 is a similar step down in the same direction. What counts is the installation date, not the date the quote was signed. A Queensland homeowner or business who is quoted for a December installation should ask, in writing, what happens to the price if the job slips into January — and should not accept a poor quote in December only because of the step-down. The step-down is real, but it is smaller than the price difference between a dear quote and a fair one, and a rushed December job that is poorly installed is worse than a well-installed January job. The Regulator's own inspection work, including the 2025–26 SRES inspection report published on 13 November 2026, is a reminder that workmanship and compliance matter as much as timing.


What this means for you

Investors and developers: A record 5 GW to the end of Q3, 5.5 GW by mid-November, and a raised lower bound on the 2026–2027 projection are a clear signal that large-scale renewable investment is being committed at a pace not seen before. More than half of the FID total to the end of Q3 was CIS-backed, which matters for revenue risk. The constraint to watch is approvals: the same report lowers the 2026 approvals projection to 2.6–3.4 GW, with only 570 MW under assessment at 30 September. A developer who reads only the FID headline will overstate how quickly the next wave can follow. Battery FID — 5.1 GW and 20 GWh in 2026, with average size more than doubled to 621 MWh — and the market figures — 48% of intervals price-setting, discharge more than tripled — describe storage becoming central to how the NEM works. This blog does not advise on any individual project; that needs project-level due diligence.


Commercial and industrial buyers in Queensland: A 27% fall in wholesale prices is a wholesale outcome, not a retail bill cut. Wholesale is only one component of a bill, alongside network charges, retail costs and other charges. It may feed into retail offers over time, but it does not automatically cut any existing contract. The most direct change for many Queensland businesses is the mid-scale SRES opening: systems over 100 kW to 1 MW installed on or after 1 October 2026 can now create STCs, with applications open since 17 November 2026. For a warehouse, manufacturer, food processor, school, hospital, shopping centre, farm or council building, that can change the economics of a system previously assessed without STCs. The benefit depends on system size, zone rating, deeming period and certificate price — it is not a fixed dollar amount. Batteries supplying 8% of evening-peak generation, ahead of gas at 1.5%, is also a business question: the evening peak is often the most expensive part of the day, and a battery that shifts daytime solar into the evening, or shaves a demand peak, can be commercially relevant — but only if the site's load profile, tariff and demand charges support it. Check the site's actual half-hourly load, not a generic profile.


Homeowners in Queensland and Brisbane: Rooftop solar had its strongest September quarter on record, and home batteries totalled 10.3 GWh installed and approved. For a Brisbane homeowner, the practical implications are timing and quality. The STC deeming period falls from five years to four years on 1 January 2027, and the battery factor falls from 6.8 to 5.7 the same day. A system installed in 2026 attracts more STCs than the same system in 2027. That is worth factoring in — but it is not a reason to rush a poor decision or accept an unchecked quote. The step-down is smaller than the price difference between a dear quote and a fair one. Brisbane is in the Energex network area in South East Queensland. The most local large-scale project in this report is Stage 3 South Pine Supernode — 1,215 MWh, adjacent to the South Pine substation north of Brisbane — which this site covered in a News blog on 24 November 2026 and which appears here only as one QCMR line. Its effect will come through the network and the market as it is built, not through any individual bill today. Ganymirra and Majors Creek are likewise large-scale projects: the QCMR gives no construction start date, completion date or cost for either, and this blog does not estimate them.


What EServices4U would check independently

Start with the documents, not the headline: A record FID year is a market signal, not a due-diligence finding for any individual project, system or quote. An independent check starts with the documents for that specific project or system: the quote or tender, the system design and single-line diagram, the equipment datasheets, the connection application and approval, the incentive calculation, and the contract terms — each checked against the relevant standard, the network's requirements, and the scheme rules as they apply on the installation date. For a large-scale or commercial system, that includes connection and approvals status, resource and yield assumptions, battery duration and sizing, and protection and earthing. For a residential system, it includes system size against actual usage, panel and inverter selection, battery size against evening load, and the STC calculation, including zone rating, deeming period and battery factor. EServices4U does not sell solar installations and does not receive installer commissions. An independent check does not guarantee savings or a payback period, and it does not certify compliance for a system that has not been checked against the applicable standards.


Frequently asked questions

What is FID, and why does the 5 GW figure matter?


FID is final investment decision — the point at which a project's owners commit the money and proceed to build. The 5 GW figure matters because it is the total large-scale renewable generation capacity that reached that point in the first nine months of 2026, already above the 2025 full-year record of 4.9 GW. It is committed investment, not power already on the grid.


Does 5 GW reaching FID mean 5 GW of new power is now generating?


No. FID is a commitment to build. Construction, connection and commissioning follow, and the QCMR's approvals figures show those steps are moving more slowly than investment decisions, with only 0.6 GW approved in Q3 and 570 MW under assessment at 30 September 2026.


Which Queensland projects reached FID in Q3 2026?


The 150 MW Ganymirra Solar Power Station and the 150 MW Majors Creek Solar Farm, both CIS-supported, and the 1,215 MWh Stage 3 South Pine Supernode battery, also CIS-supported. The 800 MWh Koolunga battery named in the same reporting is in South Australia, not Queensland.


Will wholesale prices falling 27% cut my electricity bill by 27%?


No. Wholesale prices are one component of a retail bill, alongside network charges — Energex in South East Queensland, Ergon Energy in regional Queensland — retail costs and other charges. A wholesale fall may feed into retail offers over time, but it does not cut any bill by the same percentage.


What changed for commercial solar in November 2026?


Applications opened on 17 November 2026 for STCs for mid-scale solar systems over 100 kW to 1 MW, installed on or after 1 October 2026. That band was previously above the SRES cap. The value for any system depends on its size, zone rating, deeming period and certificate price.


Should I rush a solar or battery install before 1 January 2027?


The deeming period falls from five years to four years and the battery factor from 6.8 to 5.7 on 1 January 2027, so a 2026 installation attracts more STCs. That is a real timing factor, but it is not a reason to accept an unchecked quote or a rushed, poorly installed job. Ask in writing what happens to the price if the job slips into January, and have the quote checked first.


Get an independent check before you sign

  • Start with a free 15-minute consultation to talk through your tender, system, building, or project and find out which fixed-fee review fits, if any. Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. No obligation, and it does not include a written report.

  • Residential solar quote review — from $149: an independent check of an installer's quote, system size, equipment, STC calculation and terms before you sign. See packages and pricing.

  • Solar and battery feasibility assessment — from $299: a site-specific assessment of whether solar, a battery, or both suit your home or business, based on your actual usage. See packages and pricing.

  • Home Owner's Engineer — from $599: independent engineering support through your project, reviewing the design and checking the installation against it. See owners engineer.

  • Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off — from $495: technical review and single-line diagram sign-off for commercial and industrial projects. See packages and pricing.


EServices4U is independent: it does not sell solar installations and does not receive installer commissions. Find out more about the team at EServices4U, meet the team at our team page, or start with a quote review at get a quote.