Construction Begins on Landmark NSW Battery Storage Project

Mar 1

1 min read

0

0


New England Region Advances Energy Transformation

Work has officially begun on New South Wales’ first large-scale battery energy storage system (BESS), marking a major milestone in the state’s clean energy shift.

Construction Begins on Landmark NSW Battery Storage Project
Key Project Details

🔋 Capacity: 200MW, with a two-hour storage duration

🌞 Location: ACEN Australia’s 720MW New England Solar project

⚡ Purpose: Deliver on-demand energy to NSW & Queensland


Boosting Grid Stability & Security

The 400MWh storage system will feature advanced grid-forming inverters, enhancing:

✔ System strength

✔ Network stability

✔ Security services


This is the first large-scale battery project supported by NSW’s Emerging Energy Program.


Progress & Timeline

🛠 Site preparation & electrical infrastructure: Underway

🏗 Civil & base electrical work: Starting in the next two months

🚚 Battery module delivery: Second half of 2025

🔌 Final commissioning: Mid-2025


A 250MVA transformer (261t) will be trucked in by March 2025, with EPEC managing installation and commissioning.


Industry Leaders Speak Out

🏗 Tim Greenaway (ACEN Australia): “This is a great milestone for the region and the National Electricity Market.”

🌏 Lucas Sadler (Energy Vault): “The world is watching Australia’s battery market. We’re proud to contribute to this vital project.”


Powering the Future with EServices4U

Looking for renewable energy solutions? EServices4U offers expert advice on solar, wind, and energy storage systems. Power up with us! ⚡🌱 www.eservices4u.com.au



Mar 1

1 min read

0

0

Comments

Share Your ThoughtsBe the first to write a comment.
bottom of page