Australia's Biggest Battery Rises on Stilts: Inside Quinbrook's Supernode in Brisbane

22 minutes ago
23 min read

It is reported that the largest battery in Australia is not in a city centre, a port, or a former power station site. It is sitting on stilts, on what was once a cattle farm at Brendale, north of Brisbane, beside the South Pine substation. The project is Quinbrook Infrastructure Partners' Supernode — and the story of how it got there, and what comes next, says a great deal about where Queensland's energy system is heading.


The reporting behind this blog was published on 22 November 2026 (05:27 UTC, or 15:27 Brisbane time) and updated on 23 November 2026, following a site visit and an interview with Quinbrook founder and managing partner David Scaysbrook. Where a figure comes from a company release, this blog says so; where something is undecided, it says that too. Nothing here forecasts power prices or promises returns — a 520 MW battery and a home battery share a technology family but live in very different worlds.


What happened, in short: Stages 1 and 2 of Supernode are operating, totalling 520 MW and 1,858 MWh, making it currently the country's largest battery as reported on 22 November 2026. Stage 3 is underway and, on completion — expected in the December quarter of 2027 or the March quarter of 2028 — will lift nameplate capacity to 780 MW and 3,074 MWh, according to the Quinbrook/CATL release. A GE Vernova release gives the same total as 3,075 MWh; the 1 MWh difference between the two releases is noted here rather than smoothed over. The site has room for a further 520 MW of expansion, which could be more battery storage, data centres, or a combination of the two. That last point — the data-centre option — is the part of the story that has set phones ringing in Queensland.


Quinbrook Supernode battery storage site at Brendale north of Brisbane, Australia's biggest battery

The facts at a glance

Item

Detail

Project

Supernode, Quinbrook Infrastructure Partners

Location

Brendale, north of Brisbane, adjacent to the South Pine substation and switchyard

Stages 1 and 2 (operating)

520 MW / 1,858 MWh — currently Australia's largest battery, as reported 22 Nov 2026

Stage 3 (underway)

Adds 260 MW / 1,216 MWh of four-hour storage

Total on Stage 3 completion

780 MW / 3,074 MWh (Quinbrook/CATL release); 3,075 MWh (GE Vernova release) — a 1 MWh difference between the two releases

Stage 3 completion

December quarter 2027 or March quarter 2028

Stage 3 debt financing

A$469 million, financial close announced 15 Aug 2026

Total project financing, Stages 1–3

Approximately A$1.2 billion

Investment so far

About $1.4 billion, with another $1.2–$1.5 billion possible, as reported 22 Nov 2026

Further expansion capacity

A further 520 MW, which could be battery storage, data centres, or both

Core battery supplier, all three stages

CATL

Power conversion, control and integration, all three stages

GE Vernova; Stage 3 is GE Vernova's first grid-forming battery project in Australia

Stage 3 grid milestone

Generator Performance Standards (GPS) acceptance achieved

Battery warranty

20 years on current batteries; 25 years on future storage such as the EnerQB 8-hour battery being developed by CATL and Quinbrook

Container performance

4 MW-rated storage per container has delivered 4.073 MW each over 15 months of trials and operation

Grid connection

South Pine substation, through which as much as 80% of Queensland's power can make its way

Site history

Quinbrook bought a cattle farm north of Brisbane in 2022, beside the substation

Data-centre context

Anthropic announced in September 2026 a proposed $30 billion data centre on Queensland's Darling Downs

Queensland grid context

Rio Tinto plans to close its 1,680 MW Gladstone power station in March 2029

Related Quinbrook plans

Battery storage replicating Supernode at the proposed Gladstone State Development Area (GSDA) Energy Hub Project; Project Green Poly near Townsville, including a "Supernode North"


Why Brendale, and why a cattle farm

The first thing to understand about Supernode is that its location was not chosen by a planning committee drawing circles on a map. It is reported that Quinbrook bought a cattle farm north of Brisbane in 2022 that happened to sit next to the South Pine substation and switchyard. That accident of geography turned out to be the project's defining advantage.


The South Pine substation is one of the most important pieces of electrical infrastructure in Queensland: as much as 80% of the state's power can make its way through it, according to the reporting. For a battery, that matters enormously — it is plugged into the heart of the system, not a distant limb, with lower transmission losses and, as reported, a relatively smooth approval process, because the site was already an energy node rather than a greenfield location needing new transmission lines.


There is a second, less obvious advantage. The site is near a spur off the Queensland coast to a major international telecommunications cable running down the east coast. That gives the site what Quinbrook describes as data-centre "optionality": the connectivity a data centre needs is close at hand, even though no data centre has been built there and none has been announced. It is an option, not a commitment, and the distinction matters — this blog does not claim a data centre will be built at Supernode, only that the site could host one.


The lesson applies well beyond one project: the best battery sites are where the grid is already strong and connection is straightforward — a point as true for a 5 kW home battery in a Brisbane suburb as for a 520 MW battery at Brendale. Energex (South East Queensland) and Ergon Energy (regional Queensland) each have their own connection processes and network constraints, and any serious battery proposal has to start with those realities rather than with a brochure.


The pedestal system: batteries on stilts

The most photographed detail of Supernode is also the most unusual. Each 36-tonne battery container sits on small stilts — a pedestal system that Scaysbrook calls world-leading, and which the reporting describes as world-first. The reasoning, as reported, is thoroughly practical.


The motivation was the cost of concrete. Scaysbrook described the price of concrete for poured foundations as "quite outrageous". Pouring a conventional concrete slab or foundation for every container across a site of this size would have been one of the largest single costs in the project. The pedestal system avoids most of that concrete. But the reporting makes clear the decision was not only about the upfront price. The stilts also mean quicker construction, easier maintenance, lower service costs, and easier eventual site rehabilitation — when the batteries are eventually removed, the ground underneath has not been sealed under a slab.


Quinbrook is now using the technique for all its battery projects in the United States and the United Kingdom — a sign it worked in practice, not just on paper. It is also a reminder that the battery industry in 2026 is still learning how to build at scale: the civil works underneath the containers, and the way technicians can get at them for maintenance, matter as much as the cells and inverters inside them.


There is a second design detail worth noting. The containers are placed back-to-back as mirror images, with their doors facing each other — an arrangement worked out with CATL that reduces the clearance needed between containers and frees space. On a site where the further 520 MW of expansion headroom is part of the value, that saved space is what makes the next stage physically possible without buying more land.


The performance figures are also worth noting. The 4 MW-rated storage per container has delivered 4.073 MW each over 15 months of trials and operation — better than predicted. That gap between a datasheet rating and real-world performance is something any battery buyer should care about: fifteen months of operating data tells you what a product actually does, and a quote review should check whether the warranty and performance terms in the contract match the marketing material.


The warranty picture is part of the same story. The batteries now carry a 20-year warranty, and future storage such as the EnerQB 8-hour battery being developed by CATL and Quinbrook will come with a 25-year warranty. Longer warranties matter because a battery's economics depend on how it performs in year 15, not just year one — but a warranty is only as good as the company behind it and the terms written into it: what it covers, what voids it, and how a claim is made. That applies to a home battery in Brisbane just as much as to a grid-scale battery at Brendale.


Stage 3: what is being built, and who is paying for it

Stage 3 is the part of Supernode that is still to come, and the numbers are substantial. It adds 260 MW and 1,216 MWh of four-hour storage — the battery can discharge at its rated power for four hours, which is the duration that matters most for covering the evening peak when solar output falls away and household demand rises.


Stage 3 reached financial close on A$469 million in debt financing, according to a release dated 15 August 2026. Total project financing across Stages 1 to 3 is approximately A$1.2 billion, and investment so far is about $1.4 billion, with another $1.2–$1.5 billion possible, as reported on 22 November 2026. Investment to date and project financing are different measures, and this blog does not try to reconcile them into a single figure. Taken together, they show the scale of capital now flowing into Australian battery storage, and lenders' willingness to finance it once the first stages are operating and performing.


Two suppliers sit at the centre of the project. CATL is the core energy storage system supplier for all three stages. GE Vernova provides power conversion, control and integration across all three stages. Stage 3 has achieved Generator Performance Standards (GPS) acceptance, and it will be GE Vernova's first grid-forming battery project in Australia. "Grid-forming" matters because most batteries are "grid-following" — they synchronise to the grid's existing voltage and frequency — while a grid-forming battery can help set voltage and frequency itself, providing the stability services that coal and gas plants used to provide through the spinning mass of their turbines. As Queensland's grid carries more solar and wind and less synchronous generation, that stability role becomes more valuable, and GPS acceptance means the project has demonstrated to the market operator that it meets the performance standards required to connect and operate.


Why Australia's appeal has shifted

One of the most striking parts of the reporting is how Quinbrook's priorities have changed. The United States used to be the obvious first choice for a developer of its scale. Now, as reported, Australia takes equal billing with the US and Canada combined. The reason is tariffs: under the Trump administration, tariffs have made solar panels about three times the price in Australia and batteries about 40% more expensive, as reported. When hardware costs that much more in one market than another, capital moves.


Quinbrook's scale puts that shift in context. The company has invested about US$6.9 billion — A$10.3 billion — of equity capital in 40 GW of energy infrastructure assets, according to Scaysbrook's LinkedIn entry as reported. Australia's share of that portfolio is growing because the economics have moved, not because of sentiment. For Queensland, that is both an opportunity and a warning: investment, jobs, and infrastructure on a scale the state has not seen before — but the same cost forces can move in the other direction if policy or prices change, so approvals need to stay workable, connection processes clear, and policy settings stable enough for a lender to finance a billion-dollar battery with confidence.


Scaysbrook's comments on policy are blunt, and this blog presents them as his views, not as EServices4U's position. He says the "Future Made in Australia" plan, which supports clean energy for decarbonised export industries, "is good policy [but] execution has been terrible so far" — a developer's frustration with the gap between a policy announcement and the permits, approvals, and contracts that turn it into steel in the ground. On cost, he says nothing comes close to solar plus battery storage, and on nuclear: "it doesn't come even remotely close... it's not even worth thinking about". Those are his stated views, reported from the interview, and this blog does not adopt them as its own conclusion — but the direction is clear: the developer building Australia's largest battery is putting billions of dollars behind solar plus storage, and readers should weigh that against other evidence.


The data-centre question: why the phone started ringing

The part of the Supernode story that has drawn the most attention is not the battery itself. It is what might sit next to it. In September 2026, AI giant Anthropic announced a proposed $30 billion data centre on Queensland's Darling Downs. Scaysbrook's description of the effect was vivid: "all of a sudden the phone starts to ring". Queensland, which has lagged New South Wales and Victoria in attracting data centres, may start to close that gap.


The logic is straightforward. A data centre is a very large electricity customer that needs power around the clock, with high reliability. A battery the size of Supernode, beside a substation that carries most of the state's power, is an attractive neighbour — and with the telecommunications cable spur nearby, the site looks like a place where a data centre could be powered, connected, and backed up by storage on the same site. That is the "optionality" Quinbrook refers to.


Scaysbrook says Queensland can power data centres with 100% renewables over time "in a way that doesn't leech on the grid and impact the ratepayer if it's done responsibly". That last phrase carries a lot of weight: a data centre powered by new renewables and storage that it pays for is a very different proposition from one that draws on the existing grid at peak times and leaves other customers to carry the cost of the network upgrades it requires. Queenslanders have a legitimate interest in which version arrives, and in who pays for the grid upgrades that large new loads require.


What is not decided is whether Supernode itself will sign a data-centre partner or stay a pure battery site. Scaysbrook declines to say, and says he hopes to know by the end of the first quarter of next year. This blog does not speculate on the outcome: both options remain open, and the decision will depend on commercial negotiations that have not been disclosed. Readers should treat any claim that a data centre at Supernode is a done deal — or that it will never happen — as speculation, because that is what it would be.


Quinbrook is also planning potentially three more supernodes with big batteries in eastern Australia. No locations, sizes, or timelines have been disclosed in the reporting, and this blog does not invent them. The point worth noting is the model: find a strong grid node, build a very large battery beside it, and keep the option of co-locating large new loads such as data centres.


Gladstone and Townsville: the northern story

The Supernode story does not stop at Brisbane. Two northern Queensland plans, both still proposed rather than delivered, show how Quinbrook is thinking about the state as a whole.


First, Gladstone. Rio Tinto plans to close its 1,680 MW Gladstone power station in March 2029 — a large amount of generation leaving a region that also hosts some of Australia's most energy-intensive industry. Scaysbrook says the closure creates the need for more renewables, big batteries, and even gas-powered synchronous condensers for grid stability: machines that provide the stabilising inertia and voltage support the grid used to get from spinning turbines, without generating power themselves. It is a sign of how the grid's needs are changing — not only producing more megawatt-hours, but keeping the system stable as the machines that used to do that job retire.


Quinbrook is planning battery storage replicating Supernode at its proposed Gladstone State Development Area (GSDA) Energy Hub Project. That is a plan, not a built project: the details — size, timing, financing — have not been disclosed in the reporting, and none are invented here. Gladstone is a logical place for it: a major industrial load centre, a grid that will need new sources of stability after 2029, and a state development area designed to host large energy projects. Whether it proceeds, and on what timeline, is still to be decided.


Second, Townsville and the far north. Further north, around Townsville, Quinbrook's $8 billion Project Green Poly, including a "Supernode North", aims to mine high-purity quartz, smelt it, and produce polysilicon for solar panels and semiconductors. Scaysbrook says Quinbrook owns stakes in all the quartz worth owning in north Queensland and aims to vertically integrate from quarry to polysilicon — that is, to control the supply chain from the raw material in the ground through to the finished polysilicon that goes into solar panels and chips.


That is an ambitious plan, and it should be read as an ambition rather than a certainty. Mining, smelting, and polysilicon production are each major industrial undertakings, and combining them into a single vertically integrated project is a large bet on Queensland's resources, workforce, and approvals system. The $8 billion figure is the project's stated scale, as reported, not a sum that has been spent or financed. This blog does not predict whether it will proceed, in full or in part.


Scaysbrook's summary of the northern grid is worth quoting directly: "the further you go north, the more fragile the grid becomes". Long transmission lines, large distances between generation and load, and few strong connection points make the northern grid harder to keep stable — one reason batteries and synchronous condensers matter more in the north, and one reason any regional Queensland business considering solar or storage should pay close attention to its local network conditions under Ergon Energy.


The summer grid: why batteries matter right now

Supernode's story lands in the middle of a summer in which batteries have already changed how the Australian grid behaves. The Australian Energy Market Operator's (AEMO) Summer Readiness Outlook 2026–27, published on 20 November 2026, reported that more than 6 GW of new big battery capacity has been added since December 2025. Batteries have tripled the amount of daytime energy they absorb — to 13 GWh — and are injecting 11 GWh into the 4–9 pm peak. Those are national figures, but the pattern they describe is exactly what Supernode is built for: soak up solar in the middle of the day, when it is plentiful, and release it in the evening, when the grid needs it most.


For Queensland, that pattern has a particular edge. The state has some of the best solar resources in the country and some of the highest rooftop solar penetration, so midday solar is at times so plentiful that the grid struggles to absorb it all. Big batteries such as Supernode give that midday solar somewhere useful to go. Without them, the alternative is to curtail solar — to switch it off — or to export it at low or negative prices. With them, the same energy can be shifted to the evening, when it is worth far more to the system and to consumers.


That does not mean big batteries solve every problem. AEMO's outlook is a readiness assessment, not a promise of no tight supply days, outages, or high prices. A battery is only as useful as the network it connects to, the rules it operates under, and the commercial arrangements that decide when it charges and discharges. A battery that sits idle because of a connection constraint, or is dispatched to serve its owner's revenue rather than the system's needs, is not the same as one available when the grid needs it.


The home battery boom, and the quality warning

The same months have seen a boom in home batteries, driven in large part by the federal Cheaper Home Batteries Program, which began on 1 July 2025. As reported in early November 2026, more than 600,000 batteries have now been installed — a remarkable rate of adoption that means hundreds of thousands of households own a battery for the first time.


Two changes are coming that every Queensland household considering a battery should know about. First, the Small-scale Technology Certificate (STC) step-down on 1 January 2027: the battery factor falls from 6.8 to 5.7, and solar deeming falls from 5 to 4 years, so the subsidy for a new battery and solar system will be smaller after that date. The financial case needs to be recalculated on the new figures, and any quote that uses pre-step-down pricing for a post-step-down installation should be treated with caution.


Second, the Clean Energy Regulator's (CER) Small-scale Renewable Energy Scheme (SRES) mid-scale expansion opened for applications on 17 November 2026, extending the scheme to larger systems — one reason a feasibility review done six months ago may no longer reflect the rules a project will be assessed under.


Alongside the boom, there is a quality warning that should not be ignored. The Clean Energy Regulator's 2025–26 SRES inspection report, published on 16 November 2026, found that 61.19% of inspected batteries were substandard, and 23.11% of inspected solar systems were substandard, with under 1% unsafe. Those figures relate to inspected installations only — they are not a survey of every system in the country. But they mean that, among the systems inspectors chose to examine, defects and non-compliance were common, typically installation and documentation issues — wiring, labelling, isolation, and paperwork — rather than the panels or batteries themselves being defective. That is precisely the kind of problem an independent review is designed to catch before a system is signed off and paid for in full.


What this means for you

Supernode is a grid-scale project, and most readers of this blog will never buy a 520 MW battery. But its story carries practical implications for three different audiences — and they are not the same implications.


What this means for investors and developers

  • The model is proven, and it is being repeated. Stages 1 and 2 are operating, Stage 3 is financed and underway, and the developer is planning potentially three more supernodes in eastern Australia. For investors and developers, the signal is that the "big battery beside a strong substation" model can be financed, built, and operated at scale in Queensland — and that lenders are willing to back it with hundreds of millions of dollars in debt. That does not make every battery proposal bankable: a proposal that deviates from the template should be able to explain why.

  • Construction innovation is a real source of value. The pedestal system and the back-to-back container layout are not footnotes. They reduced concrete costs, sped up construction, and freed space for expansion. For a developer, those are the kinds of savings that decide whether a project meets its return target. For an investor reviewing a project, the questions to ask are whether those savings have been independently verified and whether the maintenance and rehabilitation benefits are written into the project's costings or only into its marketing.

  • Grid-forming capability is becoming a differentiator. Stage 3's GPS acceptance and its status as GE Vernova's first grid-forming battery project in Australia put it ahead of the market. As the grid's need for stability services grows — particularly after the Gladstone closure in 2029 — batteries that can provide those services may earn revenue and secure connections that grid-following batteries cannot. A development proposal that does not address stability services, or that assumes they will be provided by someone else, is an incomplete proposal.

  • Data-centre optionality is valuable, but it is not a contract. The site's data-centre potential is real — the substation, the telecommunications spur, and the sheer scale of the battery all point the same way. But no partner has been signed, and Scaysbrook hopes to know by the end of the first quarter of next year. An investment case that assumes a data centre will be built at Supernode, or that data-centre demand will underwrite a particular revenue stream, is assuming something that has not happened. Price the option; do not bank the outcome.


What this means for commercial and industrial buyers

  • The evening peak is the problem batteries are built to solve. Stage 3's four-hour storage is aimed squarely at the 4–9 pm window. That is also the window in which many Queensland businesses face their highest demand charges. A commercial battery that can shave that peak, or shift cheap midday solar into the evening, can change a business's electricity bill in a way that a solar-only system cannot. But the size of that change depends on the business's tariff, load profile, and demand charges — not on the battery size alone — so a feasibility study has to start from the business's actual interval data.

  • Connection capacity is the first question, not the last. Supernode works because it sits beside one of the strongest substations in the state. A commercial site works the same way in miniature: what the local network can accept, what Energex or Ergon Energy will approve, and how long that approval will take are the constraints that shape the system. A quote that promises a particular battery size without evidence that the network can accept it is a quote that has skipped the most important step.

  • The mid-scale rule change matters. With the Clean Energy Regulator's SRES mid-scale expansion opening for applications on 17 November 2026, larger commercial systems may now be eligible for support that was previously limited to smaller installations. The details of eligibility, and whether a particular project qualifies, need to be checked against the current rules — not assumed from a previous project's experience.

  • Quality is a commercial risk, not just a household one. The regulator's inspection findings — 61.19% of inspected batteries substandard — should give any business pause. A commercial system is a larger investment, with more complex wiring, protection, and documentation, and the cost of getting it wrong is correspondingly larger. Independent review of a commercial tender, including the protection settings, the isolation arrangements, and the commissioning documentation, is a small fraction of the project cost and can prevent a much larger problem.


What this means for homeowners

  • Your battery and Supernode are solving the same evening problem, at different scales. When your home battery discharges between 4 pm and 9 pm, it is doing what Supernode does for the grid: shifting solar energy from the middle of the day, when it is plentiful, to the evening, when it is needed. The economics are different, the risks are different, and the payback is different — this blog makes no claim about either — but the logic is the same.

  • The STC step-down on 1 January 2027 changes the maths. The battery factor falls from 6.8 to 5.7 and solar deeming from 5 to 4 years, so the subsidy for a new battery and solar system will be smaller after 1 January 2027 than before it. Get a quote that states clearly which STC value it uses and what the system will cost after the step-down.

  • The inspection findings are a reason to check, not a reason to fear. That 61.19% of inspected batteries were found substandard does not mean your neighbour's battery is faulty. It means installation quality varies, and the difference between a good installation and a substandard one is often invisible to the homeowner — wiring inside a switchboard, a missing label, a protection setting that has not been checked. An independent review before you sign, or an inspection before you make a final payment, is the practical response.

  • Do not buy a battery because a big battery was built. Supernode's success says nothing about whether a particular home battery will suit your house, your usage, or your budget. The right question is not "batteries are booming, should I buy one?" but "what does my household use, when do we use it, what will the network allow, and what will this specific system deliver for this specific price?" That question can only be answered from your own data.

  • Brisbane buyers should ask about their network, not just their roof. In South East Queensland, Energex's network constraints and connection rules vary by suburb and even by street. A system that works well in one Brisbane suburb may face export limits or connection conditions in another. A quote that does not mention export limits, or that assumes you can export unlimited power to the grid, deserves a second look.


What EServices4U would check independently

A story like Supernode's is a useful prompt for the checks that matter on any real project — and the checks are the same in kind, whether the project is a grid-scale battery or a battery on a Brisbane roof. Here is what EServices4U would look at, independently, before advising a client to proceed with a solar or battery proposal.


  • The connection first. What has the distributor — Energex in South East Queensland, Ergon Energy in regional Queensland — actually approved, and on what conditions? Is there an export limit, a connection agreement, and a timeline? A system that cannot be connected on the terms assumed in the quote is not the system in the quote.

  • The numbers behind the headline. A battery rated at 4 MW that delivers 4.073 MW is a good story because it is backed by 15 months of operating data. A home or commercial battery deserves the same treatment: what is the rated capacity, what is the usable capacity, what does the warranty actually cover, and what evidence supports the performance claims? A datasheet is a starting point, not proof.

  • The warranty in full, not in summary. A 20-year or 25-year warranty sounds reassuring. The questions are what it covers, what voids it, who administers a claim in Australia, and whether the company behind it will still be here in a decade. Those questions apply to a household battery and to a grid-scale one alike.

  • The protection and compliance settings. For grid-scale projects, Generator Performance Standards acceptance is the formal check. For a home or commercial system, the equivalents are the inverter settings, the anti-islanding protection, the isolation arrangements, and the commissioning documentation. The regulator's inspection findings are a reminder of how often these details are where things go wrong.

  • The financial case, recalculated on current rules. The STC step-down on 1 January 2027, the mid-scale expansion that opened on 17 November 2026, and the current feed-in and tariff arrangements all change the numbers. A feasibility assessment should use the rules that will apply when the system is installed, not the rules that applied when the quote was written — and it should show its workings, so the client can see which assumption drives the result.

  • What is not guaranteed. No independent review can promise a particular saving or payback, and EServices4U does not. What it can do is test whether the assumptions behind a promised saving are reasonable, whether the system is sized to the load it is meant to serve, and whether the contract protects the buyer if the system does not perform. That is the difference between a sales claim and a checked claim — and it is the difference that matters when a family or a business is spending thousands of dollars.


These checks map to the fixed-fee services in the call to action below: a residential quote review from $149, a solar and battery feasibility assessment from $299, a Home Owner's Engineer service from $599, and a Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off from $495. The right service depends on the project, and the free 15-minute consultation is the way to find out which one fits, if any.


Frequently asked questions

Is Supernode really Australia's biggest battery?


As reported on 22 November 2026, Stages 1 and 2 total 520 MW and 1,858 MWh, making Supernode currently the country's largest battery — a snapshot in time, since other large batteries are under construction and the title may change. Stage 3 will lift Supernode to 780 MW and about 3,074–3,075 MWh, which would extend its lead.


Where is Supernode, and why there?


It is at Brendale, north of Brisbane, beside the South Pine substation and switchyard, through which as much as 80% of Queensland's power can make its way. Quinbrook bought a cattle farm beside the substation in 2022. The location gives low transmission losses and a relatively smooth approval process, and the site is near a spur to a major international telecommunications cable, which gives it data-centre optionality.


Why are the batteries on stilts?


Each 36-tonne container sits on a small pedestal system. The motivation, as reported, was the cost of concrete for poured foundations, which Scaysbrook described as "quite outrageous". The stilts also mean quicker construction, easier maintenance, lower service costs, and easier eventual site rehabilitation. Quinbrook now uses the technique for all its battery projects in the US and UK. The containers are also placed back-to-back as mirror images with facing doors, which reduces the clearance needed between them and frees space.


When will Stage 3 be finished, and how big will Supernode be then?


Stage 3 is expected to complete in the December quarter of 2027 or the March quarter of 2028. It adds 260 MW and 1,216 MWh of four-hour storage, taking the project to 780 MW and 3,074 MWh according to the Quinbrook/CATL release, or 3,075 MWh according to the GE Vernova release — a 1 MWh difference between the two releases. Stage 3 reached financial close on A$469 million in debt financing in August 2026, and total project financing across the three stages is approximately A$1.2 billion.


Will a data centre be built at Supernode?


That has not been decided, and this blog does not speculate on the outcome. Scaysbrook declines to say whether Supernode will sign a data-centre partner or stay a pure battery site, and says he hopes to know by the end of the first quarter of next year. The site has the ingredients a data centre would want — a very large battery, a major substation, and nearby telecommunications connectivity — and Anthropic's proposed $30 billion data centre on the Darling Downs, announced in September 2026, has increased interest in Queensland data-centre sites generally. But interest is not a commitment.


What is a grid-forming battery, and why does it matter?


Most batteries are grid-following: they synchronise to the grid's existing voltage and frequency. A grid-forming battery can help set voltage and frequency itself, providing the stability services that used to come from the spinning turbines of coal and gas plants. Stage 3 has achieved Generator Performance Standards acceptance and will be GE Vernova's first grid-forming battery project in Australia. As more synchronous generation retires — including the 1,680 MW Gladstone power station in March 2029 — that stability role becomes more valuable to the grid.


What does Supernode mean for my home battery decision?


Directly, very little. Supernode is a grid-scale asset, and its economics do not translate to a household system. Indirectly, it is part of the same shift: batteries are becoming the tool the grid uses to move solar energy from midday to the evening peak, and that shift affects tariffs, export arrangements, and the value of the solar your own roof produces. The practical implications are the dated ones in this blog: the STC step-down on 1 January 2027, the regulator's inspection findings, and the need to check your own network connection and load profile before buying. A feasibility assessment can test those questions for your specific home.


What is Project Green Poly, and what is "Supernode North"?


Project Green Poly is Quinbrook's proposed $8 billion project near Townsville, including a "Supernode North". It aims to mine high-purity quartz, smelt it, and produce polysilicon for solar panels and semiconductors, vertically integrating from quarry to polysilicon. It is a proposed project, not a built one, and the figures are its stated scale as reported. This blog does not predict whether it will proceed.


Talk to EServices4U before you decide

  • Start with a free 15-minute consultation to talk through your system, battery, or project and find out which fixed-fee review fits, if any. Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. No obligation, and it does not include a written report.

  • Residential solar quote review — from $149. An independent check of the quotes you have received: the panels, the inverter, the battery, the price, and whether the system suits your home. See the packages and pricing page for details.

  • Solar and battery feasibility assessment — from $299. A proper look at whether solar and storage stack up for your home or business, using your actual usage, your tariff, and the current rules — including the STC step-down coming on 1 January 2027.

  • Home Owner's Engineer — from $599. Someone on your side through the project, from design and tender review to checking the installation. Learn more on the owner's engineer page.

  • Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off — from $495. For commercial projects that need an independent technical review and, where required, RPEQ sign-off of the single-line diagram.

  • Contact: Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. Visit EServices4U to learn more about the team and the services, or start with a quote request. No savings are guaranteed, and no outcome is promised — the point of an independent review is to give you a clear, checked picture before you commit.



Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
Comments

Share Your ThoughtsBe the first to write a comment.
bottom of page