Major Milestone in Storm Recovery

SA Power Networks has successfully reconnected Hawker and Leigh Creek to the state’s electricity grid, following a devastating October 2024 storm that caused widespread outages and downed 32 transmission towers.

SA Power Restoration: Hawker & Leigh Creek Reconnected
Key Highlights

Storm Impact: The event caused more damage than SA’s 2016 blackout, leaving 1,600 customers without power.


Temporary Power Solutions: SA Power Networks set up backup generation to keep essential services running.


Restoration Efforts: Teams from across the state relocated to Hawker and Leigh Creek to assist.


Final Reconnection: A planned outage on February 15, 2025 marked the full restoration of power.



Expert Insights

Barry Murphy, SA Power Networks: "Deploying generation to three sites for months was challenging, but teamwork made it possible."


Chris Bennett, SA Power Networks: "We appreciate the community’s patience. Our priority was safe, efficient restoration."


Looking Ahead

SA Power Networks continues to work with the government and ElectraNet to strengthen SA’s long-term energy resilience.




Power Up with EServices4U

Facing energy challenges? EServices4U offers energy audits, renewable solutions, and expert consultations to cut costs & boost efficiency. Visit www.eservices4u.com.au today!



Feb 17

1 min read

0

0

Comments

Deel je gedachtenPlaats de eerste opmerking.
bottom of page