CIS Tender 12 Opens for 5 GW: What It Means for Queensland Solar, Wind and Batteries

10 minutes ago
22 min read

The headline, in one paragraph: On Friday 27 November 2026, the federal government opened Capacity Investment Scheme Tender 12, seeking up to 5 GW of new wind and solar generation across the National Electricity Market. The announcement was made by Assistant Minister for Climate Change and Energy Josh Wilson, in a media release dated 27 November 2026. The tender covers all National Electricity Market jurisdictions except New South Wales. Projects in New South Wales are directed to future New South Wales Roadmap tenders instead. This is a utility-scale tender for large solar and wind projects, and it carries two features that set it apart from earlier generation tenders: for the first time in a National Electricity Market generation tender, proponents are required to participate in the federal government's Developer Rating Scheme, and 500 MW is reserved under a dedicated First Nations Set Aside. Registrations close on 22 January 2027, bids are due on 5 February 2027, and successful proponents are to be announced in June 2027.


Why Queensland readers should read past the headline: Queensland projects are eligible under Tender 12, and Queensland holds the largest development pipeline. That makes this tender a Queensland story as much as a national one. Two Queensland solar projects — the 150 MW Ganymirra Solar Power Station and the 150 MW Majors Creek Solar Farm — had just reached final investment decision in the September quarter of 2026 under Capacity Investment Scheme support, according to the Clean Energy Regulator's Q3 2026 Quarterly Carbon Market Report, published on 26 November 2026, one day before Tender 12 opened. Queensland therefore enters this tender with recent, confirmed investment activity behind it, not only with projects still on paper. At the same time, the tender's 30 MW minimum project size means it is not a rooftop scheme, it does not change any household rebate or rooftop program, and it will not change any individual electricity bill on its own. This blog works through what opened on 27 November, figure by figure and date by date, and then asks the practical question: what does it change for an investor or developer, a commercial or industrial buyer, and a homeowner in Queensland and Brisbane?


What 5 GW means, in plain English: A gigawatt — GW — is 1,000 megawatts, and a megawatt is 1,000 kilowatts. Five gigawatts is 5,000 megawatts of new generation capacity sought under this tender. That is capacity, not energy already generated. A project that wins support under Tender 12 still has to be built, connected and commissioned before it generates power. The tender seeks generation — solar and wind — not storage on its own. Batteries are not the subject of this tender, although batteries appear in the wider market context below, and although earlier Capacity Investment Scheme tenders have sought dispatchable capacity, including storage. A reader who treats "5 GW sought" as "5 GW of new power now on the grid" will overstate what happened on 27 November: the power comes later, if projects are selected, built and connected.


Large-scale Queensland solar farm and wind turbines under a wide blue sky, representing new renewable generation sought under CIS Tender 12

What happened on 27 November 2026

The opening: The federal government opened Capacity Investment Scheme Tender 12 on Friday 27 November 2026. The announcement was made by Assistant Minister for Climate Change and Energy Josh Wilson, in a media release dated 27 November 2026. The tender is administered through the tender administrator's published tender information, including the registration form and the tender timeline. This blog relies on the minister's media release of 27 November 2026 and on that published tender information, as reported on 27 November 2026. It does not rely on speculation about which projects may bid, or on any figure that is not in those sources.


What is being sought: Up to 5 GW of new renewable energy generation — solar and wind — across the National Electricity Market. The tender is a generation tender. It seeks new generation capacity, not a fixed number of projects. The minimum project size is 30 MW, per the tender registration form as reported. That minimum sets the scale of the tender in practical terms. A 30 MW project is a large solar farm or a wind farm, not a commercial rooftop system and certainly not a household system. A single household rooftop system is measured in kilowatts. A 30 MW project is 30,000 kilowatts. The tender is therefore aimed at developers of utility-scale projects, and at the landholders, councils, communities, network businesses and investors who are involved in projects at that scale.


Where projects can be: All National Electricity Market jurisdictions except New South Wales are covered — Queensland, Victoria, South Australia, Tasmania and the Australian Capital Territory. New South Wales is excluded from this tender, and its projects are directed to future New South Wales Roadmap tenders. A New South Wales Roadmap Tender 10 is expected to open before the close of 2026, seeking 2.5 GW across New South Wales, as set out below. The point for a Queensland reader is simpler: Queensland is in. A Queensland solar or wind project of at least 30 MW can register for Tender 12, provided it meets the tender's requirements, including the Developer Rating Scheme requirement set out below.


Who is involved: The federal government is the sponsor of the Capacity Investment Scheme, and the Assistant Minister for Climate Change and Energy, Josh Wilson, is the minister who announced the opening. The tender administrator publishes the tender information, runs the registration and bidding process, and sets the dates. The Developer Rating Scheme is independently operated, and its scheme provider is the body with which a proponent must have commenced the assessment process before submitting a bid. First Nations equity participants and revenue-sharing partners are involved through the dedicated First Nations Set Aside. Landholders, councils and local communities are involved through the Developer Rating Scheme, which gives them transparent information on developer conduct. No individual developer, project, landholder or council is named in this blog as a Tender 12 participant, because no individual Tender 12 project has been awarded yet, and no Queensland project names, costs or start dates have been published for this tender. The story on 27 November is the opening of the process, not a list of winners.


What the minister said: The minister's media release of 27 November 2026 includes two statements that are quoted verbatim in this blog, because they state the government's stated purpose for the tender. The first is: "The Capacity Investment Scheme is giving investors the confidence to build the new energy Australia needs, strengthening reliability and putting downward pressure on power prices." The second is: "This next tender will unlock up to 5 gigawatts of new renewable generation to help power Australian homes and businesses for decades to come." This blog reports those statements as the minister's stated purpose. It does not treat them as a finding that power prices will fall by a particular amount, or that any individual bill will fall, because no such figure is in the sources relied on for this blog. The link between new generation and power prices runs through wholesale markets, network charges, retail costs and other charges, and a statement of purpose is not a price forecast.


The facts table

Item

Detail

Date / period

Source as reported

Tender opened

Capacity Investment Scheme Tender 12 opened, seeking up to 5 GW of new solar and wind generation across the NEM, excluding NSW

27 November 2026

Federal minister's media release, 27 Nov 2026

Announced by

Assistant Minister for Climate Change and Energy Josh Wilson

27 November 2026

Federal minister's media release, 27 Nov 2026

Jurisdictions covered

Queensland, Victoria, South Australia, Tasmania, ACT; NSW excluded, directed to future NSW Roadmap tenders

Tender 12

Tender administrator's published tender information

Capacity sought

Up to 5 GW of new renewable energy generation (solar and wind)

Tender 12

Federal minister's media release, 27 Nov 2026

Minimum project size

30 MW

Tender 12

Tender registration form, as reported

Developer Rating Scheme

First time in a NEM generation tender that proponents are REQUIRED to participate; proponents must have commenced the DRS assessment process before submitting a bid, demonstrated by a signed letter of engagement with the scheme provider

DRS introduced 29 October 2026; requirement applies to Tender 12

Federal minister's media release, 27 Nov 2026

First Nations Set Aside

500 MW reserved for projects committing to at least 5% First Nations equity participation and/or an equivalent revenue-sharing arrangement

Tender 12

Federal minister's media release, 27 Nov 2026

Registrations close

22 January 2027, 5pm AEDT

22 January 2027

Tender administrator's published tender information

Bids due

5 February 2027

5 February 2027

Tender administrator's published tender information

Successful proponents announced

June 2027

June 2027

Tender administrator's published tender information

Application window

Extended window of around 10 weeks, recognising the end-of-year holiday period

Nov 2026 to Jan 2027

Tender administrator's published tender information

Tender 9

5 GW NEM generation tender; results expected early December 2026; 500 MW First Nations set aside piloted within it

Results expected early Dec 2026

Federal minister's media release, 27 Nov 2026

Tender 10

4 GW / 16 GWh dispatchable capacity tender; 500 MW / 2 GWh First Nations set aside piloted within it

Tender 10

Federal minister's media release, 27 Nov 2026

NSW Roadmap Tender 10

Expected to open before the close of 2026, seeking 2.5 GW across NSW (generation LTESA or hybrid generation LTESA)

Expected before end of 2026

As reported 27 November 2026

What follows Tender 12

CIS approaching completion of its planned tender program; after Tender 12 the government will assess whether a further generation tender is needed in 2027 to meet scheme capacity targets; it is reported this could be the last generation tender of the scheme

Assessment after Tender 12

Federal minister's media release, 27 Nov 2026, as reported

Climate progress report

Federal government's latest annual climate progress report published, one day before Tender 12 opened; it is reported the nation remains on track for 82% renewables by 2030

26 November 2026

As reported 26 November 2026

CER Q3 2026 QCMR

Record 5 GW of renewables reached FID in first nine months of 2026 (5.5 GW by mid-November); two Queensland solar projects at 150 MW each reached FID; 1,215 MWh Stage 3 South Pine Supernode battery reached FID

Published 26 November 2026

Clean Energy Regulator, Q3 2026 QCMR

AEMO Q3 2026 market figures

Wholesale prices down 27% vs Q3 2025; batteries set prices in a record 48% of dispatch intervals

Q3 2026

AEMO, as cited in the CER Q3 2026 QCMR

Mid-scale SRES applications

Applications opened for systems 100 kW to 1 MW, fixed five-year deeming

Opened 17 November 2026

Clean Energy Regulator bulletin, 17 Nov 2026

STC step-down

Solar deeming 5 to 4 years; battery factor 6.8 to 5.7

1 January 2027

Clean Energy Regulator arrangements published for that date

SRES inspection report

Clean Energy Regulator 2025-26 SRES inspection report

Published 16 November 2026

Clean Energy Regulator

Regional feed-in tariff

6.006c/kWh

From 1 July 2026

Ergon Energy; Queensland Competition Authority determination

Federal Cheaper Home Batteries Program

Residential program, from 1 July 2025

From 1 July 2025

Clean Energy Regulator


What the Capacity Investment Scheme is, and why a tender matters

The scheme in plain English: The Capacity Investment Scheme — the CIS — is a federal scheme that supports large-scale renewable generation and storage. It does so by underwriting revenue for projects that win support under it, reducing the revenue risk that can otherwise stop a project from reaching final investment decision. Final investment decision — FID — is the point at which a project's owners commit the money and proceed to build. It is further along than an announcement, a feasibility study, or a planning application. It is not the same as construction starting, and it is not the same as the project generating power. When the Clean Energy Regulator counts capacity reaching FID, it is counting committed investment, not capacity already on the grid. When the government opens a tender seeking 5 GW, it is opening a process that may lead to investment decisions, construction and generation over the years that follow. It is not switching on 5 GW on the day the tender opens.


How a tender works: A tender is a competitive process. The government states how much capacity it is seeking, in which jurisdictions, and by when. Developers register their interest, then submit bids. The bids are assessed, and successful proponents are announced. The successful projects then proceed through their own development steps — planning, connection, financing, construction and commissioning — on their own timetables. Tender 12 follows that pattern. Registrations close on 22 January 2027 at 5pm AEDT. Bids are due on 5 February 2027. Successful proponents are to be announced in June 2027. Between the opening on 27 November 2026 and the registration close on 22 January 2027 is an extended application window of around 10 weeks, recognising the end-of-year holiday period. That extension is stated in the tender information itself: a developer who first reads the tender in late November has the Christmas and New Year period in the middle of the preparation window, and the timetable allows for that. It does not change the closing date. A registration submitted after 22 January 2027 at 5pm AEDT is late, and this blog does not suggest that a late registration would be accepted. Queensland readers should note that Queensland does not observe daylight saving, so 5pm AEDT is 4pm in Queensland on 22 January 2027. A developer should confirm the closing time in the tender administrator's published information before relying on it.


Tender 12 in the sequence: Tender 12 is not the first Capacity Investment Scheme tender. Tender 9 was a 5 GW National Electricity Market generation tender — the same size, and the same kind, as Tender 12 — and its results are expected in early December 2026, within days of Tender 12 opening. Tender 10 was a 4 GW and 16 GWh dispatchable capacity tender. That is a different kind of tender: dispatchable capacity is capacity that can be called on when needed, including storage, and it is measured in both power — gigawatts — and energy — gigawatt-hours, because both matter for storage. Tender 12 is a generation tender, measured in gigawatts of solar and wind generation. This blog does not report Tender 9's results, because they have not yet been published.


Approaching the end of the planned program: The Capacity Investment Scheme is approaching the completion of its planned tender program. After Tender 12, the government will assess whether a further generation tender is needed in 2027 to meet the scheme's capacity targets. It is reported that this could be the last generation tender of the scheme. That reporting is included here as reporting, not as a government announcement that Tender 12 is the last tender. What the sources confirm is that an assessment will follow Tender 12, and that it will consider whether a further generation tender is needed in 2027. Whether that assessment concludes that a further tender is needed, or that the targets can be met without one, is not decided. A developer who treats Tender 12 as certainly the last chance to seek support would be overstating what is known. A developer who treats it as certainly not the last chance would be understating the position. The honest statement is the one in the sources: the planned program is approaching completion, an assessment follows Tender 12, and the question of a further generation tender in 2027 is not yet decided.


The Developer Rating Scheme: the new requirement in Tender 12

What is new: For the first time in a National Electricity Market generation tender, proponents are required to participate in the federal government's Developer Rating Scheme — the DRS. That "first time" is stated in the minister's media release of 27 November 2026, and it is the clearest single difference between Tender 12 and earlier generation tenders. Earlier tenders did not carry this requirement. Tender 12 does. A developer who has bid in an earlier generation tender without going through the Developer Rating Scheme will need to do so for Tender 12.


What the scheme is: The Developer Rating Scheme was introduced on 29 October 2026. It is independently operated. It gives landholders, councils and local communities transparent information on developer conduct, character, capability, capacity, capital and community engagement. Those six words are the scheme's stated measures, as reported in the minister's release. They cover, in plain terms, how a developer behaves, whether it can be trusted, whether it has the skills and resources to deliver, whether it has the money to do so, and how it works with the people who live where its projects are built. The scheme is not a planning approval, and it is not a connection approval. It is a rating scheme, operated independently, that makes information about a developer available to the people most affected by that developer's projects.


How a proponent demonstrates participation: Proponents must have commenced the Developer Rating Scheme assessment process before submitting a bid, demonstrated by a signed letter of engagement with the scheme provider. A signed letter of engagement is a document, signed by the proponent and the scheme provider, showing that the assessment process has begun. It is not the same as a completed rating, a pass mark, or a final score. It is evidence that the process has been started. That matters for the timetable. A developer who waits until the week bids are due — 5 February 2027 — to engage with the scheme provider may not have a signed letter of engagement in time. A developer who engages early, in December 2026 or in January 2027, has a clearer path to meeting the requirement. The registration close on 22 January 2027 and the bid due date on 5 February 2027 are therefore not the only dates that matter. The date on which the developer engages with the scheme provider also matters, because it must come before the bid.


Why the minister links the scheme to communities: The minister said: "Clean energy projects work best when they are developed with communities, not simply in communities." That sentence draws a distinction between two ways of developing a project. The first — developed "with" communities — means the community is involved, informed about the developer, and able to judge the developer's conduct and capability. The second — developed "in" communities — means the project is simply located in a place, without that involvement. The Developer Rating Scheme is presented, in the minister's release, as the mechanism that supports the first approach. This blog reports that stated purpose. It does not assess whether any individual developer meets the scheme's measures, because no individual developer's rating is in the sources relied on for this blog.


The First Nations Set Aside: 500 MW reserved

What the set aside is: Tender 12 includes a dedicated First Nations Set Aside of 500 MW, reserved for projects committing to at least 5 per cent First Nations equity participation and/or an equivalent revenue-sharing arrangement. The set aside is a reservation within the 5 GW total, not an addition to it. Five hundred megawatts is 10 per cent of 5,000 megawatts. Projects that do not meet the commitment compete for the remaining capacity. Projects that do meet it can compete for the reserved capacity.


What "at least 5 per cent" means: Equity participation means a First Nations party holds an ownership share in the project. Revenue sharing means a First Nations party receives a share of the project's revenue, under an arrangement equivalent to the equity commitment. The word "and/or" matters: a project may meet the commitment through equity, through revenue sharing, or through both. The threshold is 5 per cent. A project committing to less than 5 per cent does not meet the set-aside commitment as stated. The precise form of the arrangement, and how equivalence is assessed, is a matter for the tender's terms, as published by the tender administrator. This blog does not describe a model agreement, because no such model is in the sources relied on for this blog.


Where the approach has been used before: The set-aside approach was piloted in two earlier tenders. In CIS Tender 9, 500 MW was set aside within a 5 GW generation tender. In CIS Tender 10, 500 MW and 2 GWh was set aside within a 4 GW and 16 GWh dispatchable capacity tender. Tender 12 is therefore not the first use of the approach. It is the third use, and the second use in a generation tender of the same size. A reader who wants to know how the pilot worked in Tender 9 will need to wait for the Tender 9 results, expected in early December 2026. This blog does not report the outcome of the pilot, because it has not yet been published.


Why it happened, and what it changes

The stated purpose and the day before: The minister's stated purpose is set out in the two quoted sentences above: the scheme is giving investors confidence to build, strengthening reliability and putting downward pressure on power prices, and Tender 12 will unlock up to 5 GW to help power Australian homes and businesses for decades to come. The federal government's latest annual climate progress report was published on 26 November 2026, one day before Tender 12 opened, and it is reported that the nation remains on track for 82 per cent renewables by 2030. This blog does not claim that one caused the other. It notes the sequence, because a reader following energy news in late November 2026 will have seen both: a progress report saying the nation remains on track for the 2030 target, and a tender seeking 5 GW of the generation that would contribute to that target. Whether the 82 per cent target will be met is not decided, and this blog does not predict that it will be. The progress report, as reported, says the nation remains on track. That is a statement about the current trajectory, not a guarantee of the outcome. No single outage, accident or shortfall is cited in the minister's release as the reason for opening Tender 12, and this blog does not attribute the opening to any such event.


The record investment year: The Clean Energy Regulator's Q3 2026 Quarterly Carbon Market Report, published on 26 November 2026, found a record 5 GW of renewables reached final investment decision in the first nine months of 2026, and 5.5 GW by mid-November 2026. That record is covered in depth in the site's 27 November 2026 News blog on the same report, and this blog does not re-tell that report. It references it as context, because Tender 12 opened the day after the report was published. In the September quarter of 2026 alone, 2.1 GW reached final investment decision across nine projects, and five of those nine received support under the Capacity Investment Scheme. More than half of the projects reaching final investment decision to the end of the September quarter were backed by the scheme, it is reported. The two Queensland solar projects named in that report — Ganymirra and Majors Creek, each 150 MW — were among the five scheme-supported projects in the quarter. The report also recorded the 1,215 MWh Stage 3 South Pine Supernode battery reaching final investment decision in Queensland. Those figures give Tender 12 its context: a record year for investment decisions, with the scheme already supporting a majority of the projects that reached decision, and with Queensland already represented in that record. For the full detail of that report, see the site's 27 November 2026 News blog: CER Record 5 GW FID: What It Means for Queensland Buyers.


What Tender 12 changes, and what it does not change: Tender 12 changes the opportunity for developers. From 27 November 2026, a developer with a solar or wind project of at least 30 MW in Queensland, Victoria, South Australia, Tasmania or the Australian Capital Territory can register for a tender seeking up to 5 GW, with a dedicated First Nations Set Aside of 500 MW, and with a new requirement to participate in the Developer Rating Scheme. Tender 12 does not change the planning system, the connection process, or the network. A project that wins support will still need planning approval, a connection agreement, financing, construction and commissioning. Tender 12 does not change any household rebate, any rooftop program, any feed-in tariff, or any retail price. It does not change the price any household or business pays for electricity on 28 November 2026. It does not guarantee that 5 GW will be built. It seeks up to 5 GW. The difference between "seeks" and "will build" is the difference between a tender opening and a completed project, and this blog keeps that difference in view throughout.


Queensland: why this tender matters here

Eligible, with the largest pipeline: Queensland projects can enter Tender 12, and Queensland holds the largest development pipeline. This blog does not give a figure for that pipeline, because no pipeline figure is in the sources relied on, and it does not name the projects in it, because no Tender 12 project names have been published. What can be said is that Queensland's position is not marginal: in a tender seeking 5 GW across five jurisdictions, Queensland projects are likely to be a substantial share of the bids, and of the successful projects if the bids are competitive. That is a likelihood, not a finding. The findings will come in June 2027.


Two Queensland solar projects just reached final investment decision: Ganymirra Solar Power Station and Majors Creek Solar Farm, each 150 MW and each supported by the Capacity Investment Scheme, reached final investment decision in the September quarter of 2026. Together they account for 300 MW of the 1 GW of solar that reached decision in the quarter. The report gives no construction start date, completion date or cost for either project in the reporting checked for this blog, and this blog does not estimate them. The point is that Queensland projects have already reached decision under scheme support, in the quarter immediately before Tender 12 opened. The same report recorded the 1,215 MWh Stage 3 South Pine Supernode battery, north of Brisbane, reaching final investment decision in Queensland. Its effect will come through the network and the market as it is built, not through any individual bill today.


The Developer Rating Scheme and the First Nations Set Aside matter most where the pipeline is largest: Queensland has more landholders and councils being asked to host large projects than any other jurisdiction in the tender, and the 500 MW set aside creates a distinct path for Queensland projects committing to at least 5 per cent First Nations equity participation or an equivalent revenue-sharing arrangement. Brisbane is in the Energex network area in South East Queensland. No Brisbane project name, cost or start date has been published for this tender.


What this means for you

Investors and developers: Tender 12 is a direct, dated opportunity. Registrations close 22 January 2027, bids are due 5 February 2027, and successful proponents are announced in June 2027. The first step is the Developer Rating Scheme engagement, because the assessment process must have been commenced before a bid is submitted, demonstrated by a signed letter of engagement. The second step is the First Nations question: does the project commit to at least 5 per cent equity participation or an equivalent revenue-sharing arrangement, documented to meet the tender's requirements, so it can compete for the 500 MW set aside? This blog does not advise on any individual project, and it does not describe the bid assessment criteria, because those are a matter for the tender administrator's published information.


Commercial and industrial buyers in Queensland: Tender 12 does not change your bill, tariff, or network approval, and it does not change the economics of a system on your own site. Over time, up to 5 GW of new generation, if selected, built and connected, adds generation to the market, and the minister's stated purpose is that it will strengthen reliability and put downward pressure on power prices. That pressure, if it occurs, works through wholesale prices, which are only one component of a retail bill. It will not cut any existing contract. The most direct change for many Queensland businesses is the mid-scale Small-scale Renewable Energy Scheme opening below, not Tender 12. A business considering a commercial system should have it assessed on its own interval data, tariff, and network approval.


Homeowners in Queensland and Brisbane: Tender 12 does not change anything about a household solar or battery decision. The tender's minimum is 30 MW; a household system is measured in kilowatts. It does not offer a household rebate, and it does not change the federal Cheaper Home Batteries Program, which began on 1 July 2025 and is a residential program. The household dates that do matter are below: solar deeming falls from five years to four years on 1 January 2027, and the battery factor falls from 6.8 to 5.7 the same day. A Brisbane homeowner is in the Energex area; a regional Queensland homeowner is in the Ergon Energy area, where the regional feed-in tariff is 6.006c/kWh from 1 July 2026.


Landholders, councils and communities: For you, Tender 12 is a story about process as much as power. Ask the developer whether it has commenced the Developer Rating Scheme assessment process and can show the signed letter of engagement. For a First Nations community approached about a project, ask for the equity or revenue-sharing arrangement to be stated in writing, with the percentage or equivalent share stated, and take independent legal and commercial advice before agreeing to anything.


Dated updates to keep beside this story

Mid-scale SRES, 17 November 2026: Applications opened in the REC Registry for mid-scale solar systems over 100 kW to 1 MW installed on or after 1 October 2026, with a fixed five-year deeming period. STC step-down, 1 January 2027: Solar deeming falls from five years to four years, and the battery factor falls from 6.8 to 5.7. What counts is the installation date, not the date the quote was signed. SRES inspection report, 16 November 2026: The Clean Energy Regulator published its 2025-26 SRES inspection report. Regional feed-in tariff: 6.006c/kWh from 1 July 2026. Cheaper Home Batteries Program: Federal residential battery program, from 1 July 2025. None of these is changed by Tender 12, and none should be confused with it.


What EServices4U would check independently

Start with the documents, not the headline: A tender opening is a market signal, not a due-diligence finding for any individual project, system or quote. An independent check starts with the documents for that specific project or system: the tender or quote, the system design and single-line diagram, the equipment datasheets, the connection application and approval, the incentive calculation, and the contract terms — each checked against the relevant standard, the network's requirements, and the scheme rules as they apply on the installation date. For a large-scale or commercial system, that includes connection and approvals status, resource and yield assumptions, battery duration and sizing, and protection and earthing. For a residential system, it includes system size against actual usage, panel and inverter selection, battery size against evening load, and the STC calculation, including zone rating, deeming period and battery factor. EServices4U does not sell solar installations and does not receive installer commissions. An independent check does not guarantee savings or a payback period, and it does not certify compliance for a system that has not been checked against the applicable standards.


Frequently asked questions

What is CIS Tender 12?


A federal tender opened on 27 November 2026, seeking up to 5 GW of new solar and wind generation across the National Electricity Market, excluding New South Wales, with a 30 MW minimum project size.


When do registrations close, and when are bids due?


Registrations close on 22 January 2027 at 5pm AEDT, bids are due on 5 February 2027, and successful proponents are to be announced in June 2027.


What is the Developer Rating Scheme, and why is it required?


It is an independently operated scheme, introduced on 29 October 2026, giving landholders, councils and local communities transparent information on developer conduct, character, capability, capacity, capital and community engagement. Tender 12 is the first NEM generation tender to require participation, demonstrated by a signed letter of engagement before a bid is submitted.


What is the First Nations Set Aside?


500 MW reserved for projects committing to at least 5 per cent First Nations equity participation and/or an equivalent revenue-sharing arrangement. The approach was piloted in Tender 9 and Tender 10.


Can Queensland projects enter Tender 12?


Yes. Queensland, Victoria, South Australia, Tasmania and the ACT are eligible. New South Wales projects are directed to future New South Wales Roadmap tenders, with Roadmap Tender 10 expected to open before the close of 2026, seeking 2.5 GW.


Is this the last Capacity Investment Scheme generation tender?


Not decided. The scheme is approaching the completion of its planned tender program, and after Tender 12 the government will assess whether a further generation tender is needed in 2027. It is reported this could be the last generation tender of the scheme.


Will Tender 12 cut my electricity bill?


Not directly, and not by any stated amount. It seeks generation that, if built, may put downward pressure on wholesale prices over time. Wholesale prices are only one component of a retail bill.


Does Tender 12 change household solar or battery rebates?


No. It is a utility-scale tender with a 30 MW minimum. It does not change the Cheaper Home Batteries Program, the Small-scale Renewable Energy Scheme, or any feed-in tariff.


Get an independent check before you sign

  • Start with a free 15-minute consultation to talk through your tender, system, building, or project and find out which fixed-fee review fits, if any. Call/WhatsApp 0480 001 498 or email growthpartner@eservices4u.com.au. No obligation, and it does not include a written report.

  • Residential solar quote review — from $149: an independent check of an installer's quote, system size, equipment, STC calculation and terms before you sign. See packages and pricing.

  • Solar and battery feasibility assessment — from $299: a site-specific assessment of whether solar, a battery, or both suit your home or business, based on your actual usage. See packages and pricing.

  • Home Owner's Engineer — from $599: independent engineering support through your project, reviewing the design and checking the installation against it. See owners engineer.

  • Commercial Infrastructure Assessment / RPEQ & RPEV SLD Sign-Off — from $495: technical review and single-line diagram sign-off for commercial and industrial projects. See packages and pricing.


EServices4U is based in Queensland and serves clients Australia-wide. It does not sell solar installations and does not receive installer commissions. Find out more at EServices4U, meet the team at our team page, or start with a quote review at get a quote.